Road surfacing works week commencing 27th Mar 2017

|

Pothole repairs: A TfB team use a Jet Patcher to repair a damaged road surface.

Week commencing Monday 27th March 2017 Transport for Buckinghamshire will be carrying out work at the following locations.

The dates shown are subject to change at short notice.

Carriageway Surfacing Programme

Studridge Lane, Speen : Monday 27th March 2017 to Friday 31st March 2017 – Daytime carriageway surfacing and the reinstatement of road markings using a road closure between 8.00am and 5.00pm.

Gerrards Cross Road, Stoke Poges at the junction with Templewood Lane and Stoke Common Road : Monday 27th March 2017 to Wednesday 29th March 2017 – Night time reinstatement of high friction surfacing using temporary traffic signals between 7.00pm and 6.00am.

Wingrave Road, The Green and Cublington Road, Aston Abbotts : Monday 27th March 2017 to Friday 31st March 2017 – Daytime ironwork adjustments using temporary traffic signals between 9.30am and 3.30pm.

Footway Surfacing Programme

High Street, Burnham : Monday 27th March 2017 to Tuesday 9th May 2017 – Daytime and night time carriageway and footway maintenance work including repairs to kerbing and drainage.

Burnham programme details:

  • Gore Road to Jennery Lane : Monday 27th March 2017 to Friday 14th April 2017 – 24 hour road closure excluding weekends. Works include the repairs to the blockwork tables, kerbing and drainage. The works will be carried out in isolated areas throughout this section of the High Street thus allowing access to unaffected areas.
  • Gore Road to Lincoln Hatch Lane/Windsor Lane : Monday 27th March 2017 to Friday 28th April 2017 – Restricted working between 9.30am to 4.30pm. Works include footway, kerbing, drainage and sign repairs. These will be undertaken using localised traffic and pedestrian management. Access will be maintained.
  • Gore Road to Lincoln Hatch Lane/Windsor Lane : Friday 24th April 2017 to Tuesday 9th May 2017 – Night time closure between 7.00pm to 6.00am. Works include carriageway resurfacing over the whole length of the High Street. Vehicle access will be restricted but pedestrian access will be maintained.

High Street/Market Square, Chesham : Monday 27th March 2017 to Friday 21st April 2017 – Daytime upgrade of the existing block paving along the eastern footway along with the repair of localised drainage issues, the replacement of the existing drainage channel and targeted tree maintenance work using localised footway closures and carriageway restrictions between 8.00am and 6.00pm.

Market Square, Aylesbury : Monday 27th March 2017 to Thursday 13th April 2017 – Daytime and night time targeted maintenance work to existing block paving in the carriageway and footways along with the repair of localised drainage issues and the removal of the rising bollard assembly, using localised footway closures and carriageway restrictions. Work within the carriageway will be restricted to night time working only using road closures between 6.00pm and 6.00am. Daytime working on market days will be restricted to localised footway closures between 10.00am and 4.00pm.

Heath Close, Aylesbury : Monday 27th March 2017 to Wednesday 29th March 2017 – Daytime slurry surfacing work using localised traffic management and footway closures between 7.00am and 7.00pm.

Brentwood Way, Aylesbury : Thursday 30th March 2017 to Friday 31st March 2017 – Daytime slurry surfacing work using localised traffic management and footway closures between 7.00am and 7.00pm.