Week commencing Monday 5th June 2017 Transport for Buckinghamshire will be carrying out work at the following locations.

The dates shown are subject to change at short notice.

There is no weekend working planned this week.

Surface Dressing Programme

Rignall Road, Little Hampden – The Old Gated Road to London Road, Great Missenden : Monday 5th June 2017 to Friday 9th June 2017 – Daytime surface dressing preparatory works using a daytime road closure between 9.30am and 3.30pm.

Main Road, Drayton Parslow – 30mph speed limit at western end of the village to Newton Road : Monday 5th June 2017 to Friday 9th June 2017 – Daytime surface dressing preparatory works using a daytime road closure between 9.30am and 3.30pm.

Micro-surfacing Programme

North Park, Gerrards Cross – B416 to South Park Drive : Monday 5th June 2017 to Thursday 8th June 2017 – Daytime micro-surfacing preparatory works using a daytime road closure between 7.30am and 4.30pm.

Marsham Way, Gerrards Cross – B416 to Mill Lane : Friday 9th June 2017 to Thursday 15th June 2017 – Daytime micro-surfacing preparatory works using a daytime road closure between 7.30am and 4.30pm.

Castle Street, Marsh Gibbon – Church Street to Summerstown junction : Monday 5th June 2017 to Thursday 8th June 2017 – Daytime micro-surfacing preparatory works using a daytime road closure between 7.30am and 4.30pm.

Worminghall Road, Oakley – Manor Road to 30mph speed limit sign : Friday 9th June 2017 to Thursday 15th June 2017 – Daytime micro-surfacing preparatory works using a daytime road closure between 9.30am and 3.30pm.

Footway Surfacing Programme

Market Square, Aylesbury : Monday 5th June 2017 to Friday 9th June 2017 – Daytime and night time targeted maintenance work to existing block paving in the carriageway and footways along with the repair of localised drainage issues and the removal of the rising bollard assembly, using localised footway closures and carriageway restrictions. Work within the carriageway will be restricted to night time working only using road closures between 6.00pm and 6.00am. Daytime working on market days will be restricted to localised footway closures between 10.00am and 4.00pm.

Ironwork adjustments

A416 Broad Street & Berkhampstead Road, Chesham – White Hill to Alexander Street : Thursday 8th June 2017 to Friday 9th June 2017 – Daytime ironwork adjustments using temporary traffic signals between 9.30am and 3.30pm.

New Road, Princes Risborough – Tesco Roundabout to Bell Street Roundabout : Tuesday 6th June 2017 – Daytime ironwork adjustments using two way traffic signals between 9.30am and 3.30pm.

Combe Rise, High Wycombe – Whole length of road : Tuesday 6th June 2017 – Daytime ironwork adjustments using localised traffic management between 7.00am and 7.00pm.

Mill End Road, High Wycombe – A40 to A4010 : Wednesday 7th June 2017 – Daytime ironwork adjustments using two way traffic signals between 9.30am and 3.30pm.

Chapel Lane, High Wycombe – A40 to Mill End Road : Wednesday 7th June 2017 to Thursday 8th June 2017 – Daytime ironwork adjustments using three way traffic signals between 9.30am and 3.30pm.

Chesham Lane, Chalfont St Peter – Whole length of road : Friday 9th June 2017 – Daytime ironwork adjustments using localised traffic management between 9.30am and 3.30pm.

Denham Lane, Chalfont St Peter – Whole length of road : Friday 9th June 2017 – Daytime ironwork adjustments using localised traffic management between 9.30am and 3.30pm.

Grove Lane, Chalfont St Peter – Whole length of road : Friday 9th June 2017 – Daytime ironwork adjustments using localised traffic management between 9.30am and 3.30pm.