Week commencing Monday 28th October 2019 Transport for Buckinghamshire will be carrying out work at the following locations.

The works are part of a rolling programme and, as some activities are weather dependent, dates may change at short notice.

Carriageway surfacing

A413 Wendover Bypass – London Road Roundabout to Nash Lee Rd Roundabout : Monday 28th October 2019 to Wednesday 30th October 2019 – Carriageway surfacing works including the reinstatement of road markings using a night time road closure in operation between 7.00pm and 6.00am.

Three Households / Newbarn Lane, Chalfont St Giles – Narcot Lane to Rawlings Lane : Monday 28th October 2019 to Friday 11th November 2019 – Carriageway surfacing works using a night time road closure in operation between 7.00pm and 6.00am.

Uxbridge Road, Iver – Various locations along length of road : Monday 28th October 2019 – Joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Five points Roundabout, Iver – Various locations along length of road : Monday 28th October 2019 – Joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

A421 – Bletchley side of Buckingham, Buckingham / Whaddon – Various locations along length of road : Tuesday 29th October 2019 – Joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

A421 – Tingewick side of Buckingham, Buckingham/Radclive/Tingewick – Various locations along length of road : Tuesday 29th October 2019 – Joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Buckingham Road, Aylesbury – Various locations along length of road : Wednesday 30th October 2019 – Joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Bicester Road, Quarrendon / Aylesbury – Various locations along length of road : Wednesday 30th October 2019 – Joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Bois Moor Road, Chesham – Various locations along length of road : Thursday 31st October 2019 – Joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Abbey Way Gyratory, High Wycombe – Various locations along length of road : Friday 1st November 2019 – Joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Copperkins Lane, Amersham – A416 Junction to 30/40mph limit sign : Monday 28th October 2019 to Friday 1 November 2019 – Ironwork adjustments using local traffic management and temporary traffic signals in operation between 8am and 5pm, with a road closure in operation between 9.30am and 3.30pm on Friday 1st November 2019.

Stonecroft Avenue, Iver – B470 to End : Monday 28th October 2019 – Ironwork adjustments using local traffic management in operation between 8.00am and 5.00pm.

Chartridge Lane, Chesham – West Dean Lane to Penn Avenue : Tuesday 29th October 2019 to Monday 4th November 2019 – Ironwork adjustments using local traffic management in operation between 8.00am and 5.00pm.

Footway repairs

Desborough Avenue, High Wycombe – Carver Hill Road to Suffield Road : Monday 28th October 2019 to Tuesday 12th November 2019 – Footway resurfacing using 2 way signals in operation between 9.30am to 3.30pm.

Wendover Way, Aylesbury – Between A413 and playing fields : Monday 28th October 2019 – Footway resurfacing remedial works using 2 way signals in operation between 9.30am to 4.30pm.

Traffic signal refurbishment

Market Square, Buckingham – Junction with Market Hill to Junction with Verney Close : Monday 28th October 2019 to Friday 15th November 2019 – Traffic signals refurbishment work using temporary traffic signals and local traffic management in operation between 9.30am and 3.30pm.