Road surfacing works week commencing 1st May 2017

| May 1, 2017

Pothole repairs: A TfB team use a Jet Patcher to repair a damaged road surface.

Week commencing Monday 1st May 2017 Transport for Buckinghamshire will be carrying out work at the following locations.

The dates shown are subject to change at short notice.

Carriageway Surfacing Schemes

A4010 Bradenham Road, Bradenham between Bradenham Wood Lane to West Wycombe Village : Tuesday 2nd May 2017 to Friday 5th May 2017 – Daytime footway surfacing works, as part of carriageway scheme, using temporary traffic signals between 9.30am and 3.30pm.

Footway Surfacing Schemes

High Street, Burnham between Gore Road & Lincoln Hatch Lane/Windsor Lane : Tuesday 2nd May 2017 to Friday 12th May 2017 – Daytime and night time carriageway and footway maintenance work including repairs to kerbing and drainage.

  • Gore Road to Jennery Lane : Tuesday 2nd May 2017 to Friday 12th May 2017 – 24 hour road closure excluding weekends. Works include the repairs to the blockwork tables, kerbing and drainage. The works will be carried out in isolated areas throughout this section of the High Street thus allowing access to unaffected areas.
  • Gore Road to Lincoln Hatch Lane/Windsor Lane : Tuesday 2nd May 2017 to Friday 12th May 2017 – Restricted working between 9.30am to 4.30pm. Works include footway, kerbing, drainage and sign repairs. These will be undertaken using localised traffic and pedestrian management. Access will be maintained.
  • Gore Road to Lincoln Hatch Lane/Windsor Lane : Tuesday 2nd May 2017 to Tuesday 9th May 2017 – Night time closure between 7.00pm to 6.00am. Works include carriageway resurfacing over the whole length of the High Street. Vehicle access will be restricted but pedestrian access will be maintained.

High Street/Market Square, Chesham : Tuesday 2nd May 2017 to Friday 12th May 2017 – Daytime upgrade of the existing block paving along the eastern footway along with the repair of localised drainage issues, the replacement of the existing drainage channel and targeted tree maintenance work using localised footway closures and carriageway restrictions between 8.00am and 6.00pm.

Market Square, Aylesbury : Tuesday 2nd May 2017 to Friday 12th May 2017 – Daytime and night time targeted maintenance work to existing block paving in the carriageway and footways along with the repair of localised drainage issues and the removal of the rising bollard assembly, using localised footway closures and carriageway restrictions. Work within the carriageway will be restricted to night time working only using road closures between 6.00pm and 6.00am. Daytime working on market days will be restricted to localised footway closures between 10.00am and 4.00pm.