Road surfacing works planned week commencing 5th September 2016

Week commencing Monday 5th September 2016 Transport for Buckinghamshire will be carrying out work at the following locations.
The dates shown are subject to change at short notice.
Micro-surfacing programme
Preparatory work
Chiltern Hills Rd, Beaconsfield : Monday 5th September 2016 – Daytime preparatory work in advance of micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Old End, Station Road and West Furlong, Padbury : Monday 5th September 2016 to Friday 9th September 2016 – Daytime preparatory work in advance of micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Hawthorne Road, High Wycombe : Monday 5th September 2016 – Daytime preparatory work in advance of micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Lansdell Avenue, High Wycombe : Tuesday 6th September 2016 – Daytime preparatory work in advance of micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Spearing Road and Cross Road, High Wycombe : Wednesday 7th September 2016 to Thursday 8th September 2016 – Daytime preparatory work in advance of micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Combe Rise, High Wycombe : Friday 9th September 2016 to 13/09/16 – Daytime preparatory work in advance of micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Harvey Road and Barnard Crescent, Aylesbury : Friday 9th September 2016 – Daytime preparatory work in advance of micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Micro-surfacing
Main Road, Naphill : Saturday 3rd September 2016 to Sunday 4th September 2016 – **weekend working** Daytime micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Burgess Wood Grove and Burgess Wood Road, Beaconsfield : Monday 5th September 2016 to Tuesday 6th September 2016 – Daytime micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Beechwood Road, Beaconsfield : Tuesday 6th September 2016 to Wednesday 7th September 2016 – Daytime micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Chiltern Hill Road, Beaconsfield : Wednesday 7th September 2016 to Thursday 8th September 2016 – Daytime micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Westfield Road, Beaconsfield : Thursday 8th September 2016 to Friday 9th September 2016 – Daytime micro-surfacing treatment using a daytime road closure between 8.00am and 5.00pm.
Ironwork adjustments
Church Lane and High Street, Ludgershall : Saturday 3rd September 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Chilton Road, Long Crendon : Saturday 3rd September 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Station Road, Taplow : Sunday 4th September 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Denham Lane/Chesham Lane, Chalfont St Peter : Monday 5th September 2016 to Sunday 11th September 2016 – **weekend working** Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Narcot Lane, Grove Lane and Gold Hill West, Chalfont St. Peter : Monday 5th September 2016 to Thursday 8th September 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 9.30am and 3.30pm.
Burlington Road, Burnham : Friday 9th September 2016 to Saturday 10th September 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
A4010 Chapel Lane, High Wycombe : Monday 5th September 2016 to Friday 9th September 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 9.30am and 3.30pm.
Reinstatement of road markings and road studs
Various locations – ongoing.
Plane and patch programme
The Pastures, High Wycombe : Saturday 3rd September 2016 – Daytime targeted patching work using a daytime road closure between 7.00am and 7.00pm.
Park Road, Farnham Royal : Monday 5th September 2016 to Tuesday 6th September 2016 – Daytime targeted patching work using a daytime road closure between 7.00am and 7.00pm.
Church Lane, Stoke Poges : Tuesday 6th September 2016 – Daytime targeted patching work using a daytime road closure between 7.00am and 7.00pm.
Winchendon Road, Ashendon : Wednesday 7th September 2016 to Thursday 8th September 2016 – Daytime targeted patching work using a daytime road closure between 7.00am and 7.00pm.
Frederick Street, Waddesdon : Friday 9th September 2016 – Daytime targeted patching work using a daytime road closure between 7.00am and 7.00pm.
Queen Street, Pitstone : Friday 9th September 2016 – Daytime targeted patching work using a daytime road closure between 7.00am and 7.00pm.