Roadworks for the week ahead – Monday 1st June 2020
Week commencing Monday 1st June 2020 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Road surfacing schemes
Langley Park Road, Wexham – Wood Lane to the county boundary : Monday 1st June 2020 to Friday 19th June 2020 – Resurfacing using a night time road closure between 7.00pm and 6.00am.
Tring Road, Aylesbury – King Edward Avenue to Regent Road : Monday 1st June 2020 to Friday 5th June 2020 – Resurfacing using a daytime road closure between 7.00am and 7.00pm.
Aylesbury Road, Winslow – Swanbourne junction to the entrance to town : Monday 1st June 2020 to Friday 12th June 2020 – Preparatory patching using a night time road closure between 7.00pm and 6.00am.
Lock Road, Marlow – Various locations along the road : Monday 1st June 2020 to Tuesday 2nd June 2020 – Patching using a daytime road closure and temporary traffic lights between 7.30am and 4.30pm.
Mill Road and Gossmore Lane, Marlow – Various locations along the road : Wednesday 3rd June 2020 to Friday 5th June 2020 – Patching using a daytime road closure between 7.30am and 4.30pm.
Drainage Programme
Ash Grove, Stoke Poges – Along the cul de sac : Monday 1st June 2020 to Tuesday 9th June 2020 – Drainage improvements using local traffic management between 8.00am and 5.00pm.
Mapridge Green Lane, Great Missenden – Rignall Road junction : Monday 1st June 2020 to Wednesday 17th June 2020 – Drainage improvements using temporary traffic lights between 8.00am and 5.00pm.
Orchard Road, Seer Green – Junction with School Lane : Monday 1st June 2020 to Tuesday 2nd June 2020 – Drainage improvements using temporary traffic lights between 9.30am and 3.30pm.
Lower Road, Loosley Row – Outside Loosley House : Monday 1st June 2020 to Wednesday 3rd June 2020 – Drainage improvements using temporary traffic lights between 8.00am and 5.00pm.
Bridge Improvements
High Street, Marlow – Marlow Bridge : Monday 1st June 2020 to Friday 10th July 2020 – Bridge refurbishment using a 24/7 road closure until Monday 8th June 2020 and thereafter two-way lights between 8.00am and 6.00pm until Friday 10th July 2020.
*Source of article : Buckinghamshire Council.