Road surfacing works planned from 31st July 2014 to 9th August 2014

| August 3, 2014

DrainClearanceInBakerStreet-2014-07-10-SDC11014

In the coming week Transport for Buckinghamshire (TfB) will be working on thirteen roads and three foot ways across Buckinghamshire.

The planned works are part of a rolling programme and therefore maybe subject to disruption in the event of bad weather. Currently the roads to be worked on are as follows:

Wednesday 23rd July 2014 – Monday 4th August 2014 : Latimer Road, Chenies
Daytime surfacing preparation works being carried out with a road closure, in advance of road surface dressing

Wednesday 30th July2014 – Friday 8th August 2014 : Stockwell Lane, Meadle
Daytime surfacing preparation works being carried out with a road closure, in advance of road surface dressing

Wednesday 30th July2014 – Friday 8th August 2014 : Thame Road, Long Crendon
Daytime surfacing preparation works being carried out with a road closure, in advance of road surface dressing

Thursday 31st July 2014 – Friday 15th August 2014 : A355 London Road, West Amersham
Night time surfacing works being carried out with a road closure

Monday 4th August 2014 – Friday 8th August 2014 : Oxford Road, West Wycombe
Daytime surfacing preparation works being carried out using temporary traffic lights, in advance of road surface dressing

Thursday 7 August – Friday 8 August: Padbury Road, Thornborough
Daytime surfacing preparation works being carried out using a road closure, in advance of road surface dressing

Saturday 9th August : A412 Uxbridge Road, Stoke Poges
Daytime surface dressing being carried out using lane closures

Saturday 9th August – Sunday 10th August 2014 : Denham Road, Iver
Daytime surface dressing being carried out using a combination of stop and go and convoy working (traffic is brought to a halt in advance of road works and is then led slowly in single file through the site)

Sunday 10th August 2014 : Farnham Lane, Burnham
Daytime surface dressing being carried out using a road closure

Wednesday 30th July 2014 – Tuesday 5th August 2014 : Hampden Road, Denner Hill/Hughenden Valley
Daytime drainage jetting works being carried out with an off-peak road closure as part of the Severe Weather Recovery Programme

Wednesday 6th August – Tuesday 12th August 2014 : The Vale/Vale Road, Chesham
Daytime drainage jetting works being carried out with a road closure as part of the Severe Weather Recovery Programme

Thursday 31st July 2014 – Thursday 7th August 2014 : Blackthorn Road, Marsh Gibbon
Daytime works being carried out with a road closure as part of the Severe Weather Recovery Programme

Friday 8th August 2014 – Wednesday 13th August 2014 : Townsend, Marsh Gibbon
Daytime works being carried out with a road closure as part of the Severe Weather Recovery Programme

These three foot ways are to be worked on next week as part of the 2014/2015 foot way treatment programme:

Monday 4th August 2014 – Tuesday 5th August 2014 : Page Hill Avenue, Buckingham

Wednesday 6th August 2014 – Thursday 7th August 2014 : Bates Lane, Weston Turville

Friday 8th August 2014 – Thursday 14th August 2014 : Spenser Road, Aylesbury