Road surfacing works planned from 5th December 2014 to 11th December 2014
Transport for Buckinghamshire (TfB) are still undertaking lots of work on the road network in Buckinghamshire, with potholes, street light repairs, gully emptying and minor repair work going on.
In addition, TfB completed work on a larger scale scheme at Wycombe Road, Saunderton.
Foot way works continued in the following locations:
Oak Green, Aylesbury
Old Slade Lane, Iver
Stag Lane, Great Kingshill
Fassets Road, Loudwater
Dandridge Drive/ Millside, Bourne End
The TfB LED replacement programme continued as well with 1152 lanterns replaced with new, efficient LED lamps. The scheme is 44.5% complete. The Christmas embargo has now shut down work on major roads, so the crews will be back after the Christmas season in January 2015.
– Known sites that suffer with a number of potholes
– Local Area Technicians’ knowledge of their local areas
Works will be carried out by our supply chain partners and the majority will require road closures. Works will run from December 2014 until March 2015 and will consist of patching works; from 1m² to 140m², depending on the site requirements.
Next week TfB will be visiting the following sites:
Turville Valley Road Turville : Monday 8th December 2014 – Wednesday 10th December 2014
Howard Avenue Aylesbury : Monday 8th December 2014
The Green & Brook Street Edlesborough : Tuesday 9th December 2014
Swallow Street Iver : Thursday 11th December 2014 – Friday 12th December 2014
Lower Road Gerrards Cross : Wednesday 10th December 2014
Mill Lane Gerrards Cross : Thursday 11th December 2014 – Friday 12th December 2014
These are all daytime patching works being carried out utilising a road closure
Chiltern Road Ballinger : Wednesday 10th December 2014
These are daytime patching works
Horton Road Ivinghoe : Thursday 11th December 2014 – Friday 12th December 2014
These are daytime patching works being carried out utilising an off peak road closure
Larger scale works are continuing on roads not covered by the Christmas embargo :
Pound Lane, Marlow : Ongoing – Friday 12th December 2014
These are daytime surfacing works being carried out utilising a road closure
The surfacing and drainage element of the TfB Severe Weather Recovery Scheme (SWRS) also continues next week. As it stands currently works scheduled for next week are as follow s:
Hampden Road, Hampden : Ongoing – Monday 8th December 2014
These are daytime works being carried out utilising a road closure
Wood Lane, Iver : w/c Monday 8th December 2014 (date TBC)
These are restricted daytime works being carried out utilising temporary traffic lights