Road surfacing works week commencing 7th Nov 2016
Week commencing Monday 7th November 2016 Transport for Buckinghamshire will be carrying out work at the following locations.
The dates shown are subject to change at short notice.
Conventional Surfacing Programme
Gerrards Cross Road, Stoke Poges : Monday 7th November 2016 to Friday 11th November 2016 – Night time surfacing work and the reinstatement of road markings using a night time road closure between 7.00pm and 6.00am.
Micro-surfacing Programme
Ironwork Adjustments
Totteridge Drive and Service Road, High Wycombe : Saturday 5th November 2016 to Sunday 6th November 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Beech Tree Road, Holmer Green : Saturday 5th November 2016 to Tuesday 8th November 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Primrose Hill, Widmer End : Saturday 5th November 2016 to Saturday 12th November 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Trinity Road, Hazlemere : Monday 7th November 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Beaumont Way, Hazlemere : Tuesday 8th November 2016 to Wednesday 9th November 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Church Lane, Padbury : Wednesday 9th November 2016 to Thursday 10th November 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Calvert Road, Middle Claydon : Thursday 10th November 2016 to Saturday 12th November 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Old End, Padbury : Friday 11th November 2016 to Monday 14th November 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Reyners Green, Little Kingshill : Sunday 13th November 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.
Reinstatement of Road Markings and Road Studs
Various locations.
Plane and Patch Programme
Hulcott Lane, Hulcott : Monday 7th November 2016 – Daytime targeted patching work using a daytime road closure between 7.00am and 7.00pm.
Footway Surfacing Programme
Narbeth Drive, Aylesbury : Saturday 5th November 2016 to Friday 11th November 2016 – Daytime preparatory works and slurry surfacing using localised footway closures between 7.00am and 7.00pm.
Henry Road, Aylesbury : Saturday 5th November 2016 to Friday 11th November 2016 – Daytime preparatory works and slurry surfacing using localised footway closures between 7.00am and 7.00pm.
Pevensey Close, Midhurst Close and Heath Close, Aylesbury : Monday 7th November 2016 to Friday 11th November 2016 – Daytime preparatory works and slurry surfacing using localised footway closures between 7.00am and 7.00pm.
Broadway, Amersham : Monday 7th November 2016 to Friday 11th November 2016 – Daytime footway surfacing using localised footway closures and parking suspensions between 7.00am and 7.00pm.
Great Hivings, Chesham : Monday 7th November 2016 to Friday 11th November 2016 – Daytime footway surfacing using localised footway closures and parking suspensions between 7.00am and 7.00pm.