Road surfacing works week commencing 23rd Jan 2017
Week commencing Monday 23rd January 2017 Transport for Buckinghamshire will be carrying out work at the following locations.
The dates shown are subject to change at short notice.
Conventional surfacing programme
Wing Road/High Street, Cublington : Monday 23rd January 2017 – Daytime surfacing work and the reinstatement of road markings using a road closure between 7.00am and 7.00pm.
Meadow Cottages, Little Kingshill (cul-de-sac) : Tuesday 24th January 2017 to Wednesday 25th January 2017 – Daytime surfacing work and the reinstatement of road markings using localised traffic management between 7.00am and 7.00pm.
Mount Street, Aylesbury (cul-de-sac) : Thursday 26th January 2017 to Monday 30th January 2017 – Daytime surfacing work and the reinstatement of road markings using localised traffic management between 7.00am & 7.00pm & lane closures on the A41 Friarage Road between 9.30am and 3.30pm.
Mill Way, Aylesbury (cul-de-sac) : Thursday 26th January 2017 to Monday 30th January 2017 – Daytime surfacing work and the reinstatement of road markings using localised traffic management between 7.00am & 7.00pm & lane closures on the A41 Friarage Road between 9.30am and 3.30pm.
Pothole Action Fund programme
Daleside, Gerrards Cross : Monday 23rd January 2017 – Daytime targeted patching work using a road closure between 7.00am and 7.00pm.
Bull Lane, Gerrards Cross : Tuesday 24th January 2017 – Daytime targeted patching work using a road closure between 9.30am and 3.30pm.
Denham Lane, Chalfont St Peter : Wednesday 25th January 2017 – Daytime targeted patching work using a road closure between 9.30am and 3.30pm.
Longbottom Lane, Beaconsfield : Thursday 26th January 2017 to Friday 27th January 2017 – Daytime targeted patching work using a road closure between 9.30am and 3.30pm.