Road surfacing works week commencing 4th Sep 2017
Week commencing Monday 4th September 2017 Transport for Buckinghamshire will be carrying out work at the following locations.
The dates shown are subject to change at short notice.
Conventional Surfacing Programme
Brook End, Weston Turville – Roundabout at junction with New Road : Wednesday 6th September 2017 to Friday 8th September 2017 – Resurfacing works using a 24 hour road closure from 6.00am on Wednesday 6th September up to 7.00pm on the Friday 8th September. Temporary traffic signals will also be in use throughout this period to allow limited use of the roundabout whilst the new surfacing treatment is curing.
Watchet Lane/Sawpit Hill, Holmer Green – Beech Tree Road to Holmer Green Road : Thursday 7th September 2017 to Friday 8th September 2017 – Night time resurfacing works using a night time road closure between 7.00pm and 6.00am.
Sawpit Hill/Holmer Green Road, Holmer Green – Roundabout at junction with Western Dene : Saturday 9th September 2017 to Monday 11th September 2017 – Resurfacing works using a 24 hour road closure from 6.00am on Saturday 9th September up to 6.00am on Monday 11th September. Temporary traffic signals will also be in use throughout this period to allow limited use of the roundabout whilst the new surfacing treatment is curing.
Micro Surfacing Programme
A4155 Henley Road, Medmenham – from the SAS Roundabout to The Dog and Badger PH : Saturday 9th September 2017 to Tuesday 12th September 2017 – Micro surfacing works using a day time road closure between 9.30am and 3.30pm.
Town Lane, Wooburn Green – Various locations along whole length : Thursday 7th September 2017 to Saturday 9th September 2017 – Daytime ironwork adjustments using temporary traffic signals between 9.30am and 3.30pm.