Roadworks for the week ahead – Mon 26th Nov 2018

| November 25, 2018

Week commencing Monday 26th November 2018 Transport for Buckinghamshire will be carrying out work at the following locations.

The works are part of a rolling programme and, as some activities are weather dependent, dates may change at short notice.

Carriageway Surfacing Schemes

Hitcham Road, Taplow/Burnham – A4 Bath Road to Boundary Road : Tuesday 27th November 2018 to Friday 30th November 2018 – Conventional Surfacing works taking place using a night time road closure between 7.00pm and 6.00am.

Knights Hill, High Wycombe – Whole length of road : Monday 26th November 2018 – Patch repair works taking place using a day time road closure between 7.00am and 7.00pm.

Footway Surfacing Schemes

Thame Road, Longwick – Walnut Tree Lane to Red Lion PH : Monday 26th November 2018 to Monday 3rd December 2018 – Footway reconstruction works taking place using two way traffic signals between 9.30am and 3.30pm.

Herons Place, Marlow – Whole length of road : Monday 26th November 2018 to Friday 7th December 2018 – Footway reconstruction works taking place using two way traffic signals between 7.30am and 4.30pm.

Limes Avenue, Aylesbury – Whole length of road : Monday 26th November 2018 to Friday 14th December 2018 – Footway reconstruction works taking place using localised traffic management between 7.30am and 4.30pm.

Beaufort Close, Aylesbury – Whole length of road : Monday 26th November 2018 to Friday 14th December 2018 – Footway reconstruction works taking place using localised traffic management between 7.30am and 4.30pm.

Chesham Lane, Chalfont St Peter – Rickmansworth Lane to Foxdell Way : Monday 26th November 2018 to Friday 21st December 2018 – Footway reconstruction works taking place using two way traffic signals between 9.30am and 4.30pm.

Wychwood Rise, Great Missenden – Whole length of road : Tuesday 27th November 2018 to Monday 10th December 2018 – Footway reconstruction works taking place using two way traffic signals between 7.30am and 4.30pm.

Safety Barrier Programme

A421, Tingewick – Tingewick Roundabout to Finmere Roundabout : Monday 26th November 2018 to Friday 30th November 2018 – Safety barrier improvement works taking place using a lane closure between 9.30am and 3.30pm.