Week commencing Monday 8th April 2019 Transport for Buckinghamshire will be carrying out work at the following locations.

The works are part of a rolling programme and, as some activities are weather dependent, dates may change at short notice.

Carriageway surfacing

Main Street, Mursley – Swanbourne Road to sports pavilion : Monday 8th April 2019 to Thursday 18th April 2019 – Conventional resurfacing taking place using a day time road closure between 7.30am and 6.00pm.

Deanshanger Road, Lillingstone Lovell – A413 to County Boundary : Monday 8th April 2019 to Monday 15th April 2019 – Surface dressing prep works taking place using a day time road closure between 7.00am to 7.00pm.

Copperkins Lane, Amersham – Deep Acres to Amersham Road : Monday 8th April 2019 to Tuesday 9th April 2019 – Micro surfacing prep works taking place using a day time road closure between 7.00am to 7.00pm.

Fowler Road Side Roads, Aylesbury – Whole length of road : Monday 8th April 2019 to Friday 12th April 2019 – Micro surfacing prep works taking place using a day time road closure between 7.00am to 7.00pm.

Heathway, Iver – Whole length of road : Wednesday 10th April 2019 to Thursday 11th April 2019 – Micro surfacing prep works taking place using a day time road closure between 7.00am to 7.00pm.

Carriageway surfacing – Plane and Patch Programme

Little London/The Firs, Whitchurch – Various locations along length of road : Monday 8th April 2019 – Plane and Patch works taking place using a day time road closure between 8.00am and 4.00pm.

Sedgemoor Road, Flackwell Heath – Various locations along length of road : Monday 8th April 2019 to Tuesday 9th April 2019 – Plane and Patch works taking place using a day time road closure between 8.00am and 5.00pm.

Belgrave Road, Aylesbury – Various locations along length of road : Monday 8th April 2019 to Wednesday 10th April 2019 – Plane and Patch works taking place using a day time road closure between 9.30am and 3.30pm.

St Mary’s Road, Wexham – Various locations along length of road : Monday 8th April 2019 to Wednesday 10th April 2019 – Plane and Patch works taking place using a day time road closure between 8.00am and 6.00pm.

Whitchurch Lane, Oving – Various locations along length of road : Tuesday 9th April 2019 to Thursday 11th April 2019 – Plane and Patch works taking place using a day time road closure between 9.30am and 3.30pm.

Straight Bit, Flackwell Heath – Various locations along length of road : Wednesday 10th April 2019 to Friday 12th April 2019 – Plane and Patch works taking place using a day time road closure between 9.30am and 3.30pm.

North Marston Lane, Whitchurch – Various locations along length of road : Wednesday 10th April 2019 to Monday 15th April 2019 – Plane and Patch works taking place using a day time road closure between 9.30am and 3.30pm.

Huntercombe Lane South, Burnham – Various locations along length of road : Thursday 11th April 2019 to Friday 12th April 2019 – Plane and Patch works taking place using two way traffic signals between 8.00am and 4.00pm.

Station Road, Haddenham – Various locations along length of road : Thursday 11th April 2019 to Friday 12th April 2019 – Plane and Patch works taking place using localised traffic management between 9.30am and 3.30pm.

Spicketts Lane, Cuddington – Various locations along length of road : Friday 12th April 2019 – Plane and Patch works taking place using localised traffic management between 8.00am and 6.00pm.

Footway surfacing

High Street, Chesham – White Hill to The Broadway : Monday 8th April 2019 to Friday 26th April 2019 – Footway block paving and drainage works taking place using a footway and road closure between 8.00am and 6.00pm.