Roadworks for the week ahead – Mon 17th June 2019

| June 17, 2019

Week commencing Monday 17th June 2019 Transport for Buckinghamshire will be carrying out work at the following locations.

The works are part of a rolling programme and, as some activities are weather dependent, dates may change at short notice.

Carriageway surfacing

Buckingham Ring Road, Buckingham – Gawcott Roundabout to Tingewick Road Roundabout : Saturday 15th June 2019 to Friday 21st June 2019 – Conventional surfacing works taking place using a night time road closure between 7.00pm to 6.00am.

Radclive Road, Gawcott – Gawcott to Gawcott village : Monday 17th June 2019 – Surface dressing preparatory patching works taking place using a day time road closure between 8.00am to 4.00pm.

Nightingales Lane, Little Chalfont – A413 to Cokes Lane : Monday 17th June 2019 to Wednesday 19th June 2019 – Surface dressing preparatory patching works taking place using a day time road closure between 9.30am to 3.30pm.

High Street, Cheddington – Tennis Courts to B489 : Monday 17th June 2019 to Friday 21st June 2019 – Surface dressing preparatory patching works taking place using a day time road closure between 7.00am to 7.00pm.

Hampden Road , Great Hampden – Bryants Bottom Road to Hampden Cross roads : Tuesday 18th June 2019 to Monday 24th June 2019 – Surface dressing preparatory patching works taking place using a day time road closure between 8.00am to 4.00pm.

Narcot Lane, Chalfont St Giles – Narcot Road to Woodlands Farm : Thursday 20th June 2019 to Friday 28th June 2019 – Surface dressing preparatory patching works taking place using a day time road closure between 9.30am to 3.30pm.

Main Street, Twyford – Portway Road to School Lane : Monday 17th June 2019 to Tuesday 18th June 2019 – Micro-surfacing works taking place using a day time road closure between 9.30am to 3.00pm.

School Lane, Twyford – Main Street to End : Monday 17th June 2019 to Tuesday 18th June 2019 – Micro-surfacing works taking place using a day time road closure between 9.30am to 4.00pm.

Church Street, Twyford – Main Street to End : Monday 17th June 2019 to Tuesday 18th June 2019 – Micro-surfacing works taking place using a day time road closure between 9.30am to 4.00pm.

Coates Lane, Downley – Littleworth Road to Manor Gardens : Monday 17th June 2019 to Tuesday 18th June 2019 – Micro-surfacing preparatory works taking place using a day time road closure between 7.30am to 7.00pm.

Portway Road, Twyford – Main Street to Gawcott Road : Tuesday 18th June 2019 to Wednesday 19th June 2019 – Micro-surfacing works taking place using a day time road closure between 9.30am to 4.00pm.

Coningsby Road, High Wycombe – Green Hill to Hamilton Road : Wednesday 19th June 2019 – Micro-surfacing preparatory works taking place using a day time road closure between 7.30am to 7.00pm.

Eastern Dene, Hazlemere – A404 to Holmer Green Road : Thursday 20th June 2019 to Friday 21st June 2019 – Micro-surfacing preparatory works taking place using a day time road closure between 7.30am to 7.00pm.

Western Lane, Winslow – Burleys Road to Missenden Road : Saturday 22nd June 2019 – Micro-surfacing preparatory works taking place using a day time road closure between 7.00am to 7.00pm.

Missenden Road, Winslow – Burleys Road to Western Lane : Saturday 22nd June 2019 – Micro-surfacing preparatory works taking place using a day time road closure between 7.00am to 7.00pm.

Demoram Close, Winslow – Western Lane to end : Saturday 22nd June 2019 – Micro-surfacing preparatory works taking place using a day time road closure between 7.00am to 7.00pm.

Abbotts Way, Wingrave – Winslow Road to End : Sunday 23rd June 2019 – Micro-surfacing preparatory works taking place using a day time road closure between 7.00am to 7.00pm.

Highway structures maintenance

Chapel Lane, High Wycombe – Gallows Lane Junction – Toweridge Lane Junction : Monday 20th May 2019 to Friday 28th June 2019 – Major maintenance to concrete retaining wall using two way traffic signals between 9.30am and 3.30pm.

Chapel Road, Ford (near Aylesbury) – Bridge over the Meadle Brook : Monday 17th June 2019 to Friday 5th July 2019 – Bridge wing wall reconstruction using local traffic management between 7.30am and 6.00pm.

Drainage work

Waterside, Chesham – Junction with Pheasant Rise : Monday 17th June 2019 to Friday 21st June 2019 – Drainage Improvement Works using 2 way traffic signals between 9.30am and 3.30pm.

Flaunden Hill, Latimer – Outside Home Farm : Wednesday 19th June 2019 to Tuesday 25th 2019 – Drainage Improvement Works using road closure in operation 24 hrs each day.