Micro Surfacing Programme
Chearsley Road, Long Crendon – Various locations : Monday 9th November 2020 to Tuesday 10th November 2020 – Carriageway iron works using localised traffic management in operation between 7.00am and 7.00pm.
Ickford Road, Shabbington – Various locations : Tuesday 10th November 2020 to Friday 13th November 2020 – Carriageway iron works using a daytime road closure on the 11 and 12 November 2020 and localised traffic management in operation between 7.00am and 7.00pm.
Crendon Road, Shabbington – Various locations along length of road : Thursday 12th November 2020 to Monday 16th November 2020 – Carriageway iron works using a daytime road closure on the 12th and 13th November 2020 and localised traffic management in operation between 7.00am and 7.00pm.
Joint sealing Programme
B4009 Lower lcknield Way, Pitch Green – Junction with Chinnor Road and Lower Icknield Way : Monday 9th November 2020 – Carriageway joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.
B4009 Lower lcknield Way, Longwick – Approaches to junction with Chestnut Way : Tuesday 10th November 2020 – Carriageway joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.
Longwick Road, Princes Risborough – Lower Icknield Way to railway bridge : Wednesday 11th November 2020 – Carriageway joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.
Coombe Lane, Naphill – Main Road to Valley Road : Thursday 12th November 2020 – Carriageway joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.
A40 West Wycombe Road, High Wycombe – Roundabout at A4010 to Portway Drive : Friday 13th November 2020 – Carriageway joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.
Bridge Improvement Programme
B488 Horton Road, Ivinghoe – 200m either side of the Grand Union Canal bridge : Monday 9th November 2020 to Friday 20th November 2020 – Bridge strengthening repairs using a 24 hour closure.
Station Road, Loudwater – A40 junction with Station Road : Monday 9th November 2020 to Friday 4th December 2020 – Retaining wall refurbishment using temporary traffic signals in operation 24 / 7.
Footway Structural Repair Programme
Cottesloe Road, Aylesbury – Churchill Avenue to Clover Lane : Monday 9th November 2020 to Friday 27th November 2020 – Footway improvement works using localised traffic management in operation between 7.30am and 4.30pm.
London Road, Great Missenden – School playing field entrance to fire station : Monday 9th November 2020 to Friday 20th November 2020 – Footway improvement works using temporary traffic signals in operation between 9.30am and 3.30pm (3.00pm during school term time).
Drainage Improvement Schemes
Missenden Road/Wey Lane / Church Street, Chesham : Monday 9th November 2020 to Wednesday 23rd December 2020 – Installation of new culvert using a road closure in operation 24 / 7.
Covid – Active Travel Plan
Southcourt, Aylesbury – Various locations : Monday 9th November 2020 to Tuesday 10th November 2020 – Pop up cycle way / planters for point closures / lining works and additional signage using mobile works and temporary traffic signals in operation between 8.00am and 4.00pm.
A40 London Road corridor improvements project
A40 London Road, High Wycombe – Micklefield Junction : Friday 13th November 2020 – Footway works to facilitate remedial civils and lining works using a Westbound Lane closure for short durations and narrow lanes on the Eastbound section between 9.30am and 3.30pm.
*Source of article : Buckinghamshire Council.