Roadworks for the week ahead – Monday 9th November 2020

| November 7, 2020

Week commencing Monday 9th November 2020 Transport for Buckinghamshire will be carrying out work at the following locations.

The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.

Micro Surfacing Programme

Chearsley Road, Long Crendon – Various locations : Monday 9th November 2020 to Tuesday 10th November 2020 – Carriageway iron works using localised traffic management in operation between 7.00am and 7.00pm.

Ickford Road, Shabbington – Various locations : Tuesday 10th November 2020 to Friday 13th November 2020 – Carriageway iron works using a daytime road closure on the 11 and 12 November 2020 and localised traffic management in operation between 7.00am and 7.00pm.

Crendon Road, Shabbington – Various locations along length of road : Thursday 12th November 2020 to Monday 16th November 2020 – Carriageway iron works using a daytime road closure on the 12th and 13th November 2020 and localised traffic management in operation between 7.00am and 7.00pm.

Joint sealing Programme

B4009 Lower lcknield Way, Pitch Green – Junction with Chinnor Road and Lower Icknield Way : Monday 9th November 2020 – Carriageway joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

B4009 Lower lcknield Way, Longwick – Approaches to junction with Chestnut Way : Tuesday 10th November 2020 – Carriageway joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Longwick Road, Princes Risborough – Lower Icknield Way to railway bridge : Wednesday 11th November 2020 – Carriageway joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Coombe Lane, Naphill – Main Road to Valley Road : Thursday 12th November 2020 – Carriageway joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

A40 West Wycombe Road, High Wycombe – Roundabout at A4010 to Portway Drive : Friday 13th November 2020 – Carriageway joint sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Bridge Improvement Programme

B488 Horton Road, Ivinghoe – 200m either side of the Grand Union Canal bridge : Monday 9th November 2020 to Friday 20th November 2020 – Bridge strengthening repairs using a 24 hour closure.

Station Road, Loudwater – A40 junction with Station Road : Monday 9th November 2020 to Friday 4th December 2020 – Retaining wall refurbishment using temporary traffic signals in operation 24 / 7.

Footway Structural Repair Programme

Cottesloe Road, Aylesbury – Churchill Avenue to Clover Lane : Monday 9th November 2020 to Friday 27th November 2020 – Footway improvement works using localised traffic management in operation between 7.30am and 4.30pm.

London Road, Great Missenden – School playing field entrance to fire station : Monday 9th November 2020 to Friday 20th November 2020 – Footway improvement works using temporary traffic signals in operation between 9.30am and 3.30pm (3.00pm during school term time).

Drainage Improvement Schemes

Missenden Road/Wey Lane / Church Street, Chesham : Monday 9th November 2020 to Wednesday 23rd December 2020 – Installation of new culvert using a road closure in operation 24 / 7.

Covid – Active Travel Plan

Southcourt, Aylesbury – Various locations : Monday 9th November 2020 to Tuesday 10th November 2020 – Pop up cycle way / planters for point closures / lining works and additional signage using mobile works and temporary traffic signals in operation between 8.00am and 4.00pm.

A40 London Road corridor improvements project

A40 London Road, High Wycombe – Micklefield Junction : Friday 13th November 2020 – Footway works to facilitate remedial civils and lining works using a Westbound Lane closure for short durations and narrow lanes on the Eastbound section between 9.30am and 3.30pm.

*Source of article : Buckinghamshire Council.