Week commencing Monday 23rd November 2020 Transport for Buckinghamshire will be carrying out work at the following locations.

The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.

Conventional Surfacing Programme

Townsend Road, Chesham – Broad Street to Bellingdon Road : Monday 23rd November 2020 – Carriageway surfacing works using a road closure in operation between 7.30am and 6.00pm.

Station Road, Beaconsfield – London End to 2nd entrance on Grove Road : Wednesday 25th November 2020 to Wednesday 16th December 2020 – Carriageway surfacing works using a road closure in operation between 7.30am and 6.00pm.

Micro Surfacing Programme

Queens Road / Harlow Road, High Wycombe – Various locations along length of road : Monday 23rd November 2020 to Wednesday 25th November 2020 – Carriageway Iron Works using localised traffic management and temporary traffic signals with a road closure in operation on Queens Road on Tuesday 24th between 7.00am and 7.00pm.

Kelvin Close, High Wycombe – Various locations along length of road : Wednesday 25th November 2020 – Carriageway Iron Works using localised traffic management and temporary traffic signals in operation between 7.00am and 7.00pm.

Woodlands, Gerrards Cross – Various locations along length of road : Thursday 26th to Friday 27th November 2020 – Carriageway Iron Works using localised traffic management in operation between 8.00am and 4.00pm.

Lovel Road, Chalfont St Peter – Various locations along length of road : Saturday 28th November 2020 – Carriageway Iron Works using localised traffic management in operation between 7.00am and 7.00pm.

Bridge Improvement Programme

Station Road, Loudwater – A40 Junction with Station Road : Monday 23rd November 2020 to Friday 4th December 2020 – Retaining Wall Refurbishment using temporary traffic signals in operation 24 / 7.

Footway Structural Repair Programme

Cottesloe Road, Aylesbury – Churchill Avenue to Clover Lane : Monday 23rd November 2020 to Friday 27th November 2020 – Footway Improvement works using localised traffic management in operation between 7.30am and 4.30pm.

London Road, Great Missenden – School Playing Field Entrance to Fire Station : Monday 23rd November 2020 – Footway Improvement works using temporary traffic signals in operation between 9.30am and 3.30pm (3.00pm during school term time).

Coombe Gardens, Hughenden – Coombe Hill to Wedgewood Drive : Monday 23rd November 2020 to Friday 4th December 2020 – Footway Improvement works using localised traffic management in operation between 7.30am and 4.30pm.

Wedgewood Drive, Hughenden – Coombe Hill to Trees Avenue : Monday 23rd November 2020 to Friday 4th December 2020 – Footway Improvement works using localised traffic management in operation between 7.30am and 4.30pm.

Drainage Improvement Schemes

Missenden Road / Wey Lane / Church Street, Chesham : Monday 23rd November 2020 to Wednesday 23rd December 2020 – Installation of new culvert using a road closure in operation 24 / 7.

A4020 Oxford Road, Denham : Monday 23rd November 2020 – Jetting Investigation Works using lane closures in operation between 9.30am and 3.30pm.

Iver lane, Iver : Monday 23rd November 2020 to Tuesday 24th November 2020 – Jetting, CCTV and drainage ditch clearance works using 2 way traffic lights in operation between 9.30am to 3.30pm.