Week commencing Monday 15th March 2021 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Conventional Surfacing Programme
Ledborough Lane, Beaconsfield – B474 Penn Road to A355 Amersham Road : Thursday 18th March 2021 to Saturday 22nd May 2021 – Carriageway reconstruction works using a road closure in operation 24 / 7.
Surface Dressing Programme
A421 Bletchley Road, Whaddon – Whaddon Roundabout to Bottledump Roundabout : Monday 15th March 2021 until Friday 19th March 2021 – Preparatory patching works using a daytime road closure in operation between 9.30am and 3.30pm.
A4155 Henley Road, Hambleden – Skirmett Road to Icehouse Lane : Monday 15th March 2021 to Friday 26th March 2021 – Preparatory patching works using a daytime road closure in operation between 9.30am and 3.30pm.
Thame Road, Brill – The Old Chapel to B4011 : Monday 15th March 2021 to Wednesday 31st March 2021 – Preparatory patching works using a daytime road closure in operation between 7.30am and 4.30pm.
Dancers End Lane, Dancers End – Lower Icknield Lane to county boundary : Monday 15th March 2021 to Thursday 18th March 2021 – Preparatory patching works using a daytime road closure in operation between 7.30am and 4.30pm.
Plane and Patch Programme
Gold Hill East – Gold Hill North Junction to Austenwood Close : Friday 19th March 2021 to Friday 26th March 2021 – Patching works using a night time road closure in operation between 7.30pm and 6.00am.
Footway Structural Repair Programme
Wendover Road, Aylesbury – Camborne Avenue to Eascote Road : Monday 15th March 2021 to Friday 19th March 2021 – Footway reconstruction works using lane controls in operation between 7.30am and 4.00pm.
Desborough Avenue, High Wycombe – Deeds Grove to Kitchener Road : Monday 15th March 2021 to Monday 5th April 2021 – Footway reconstruction works using footway closures and temporary traffic signals in operation between 9.30am and 4.00pm.
Poles Hill, Chesham – Darvell Drive to Chapmans Crescent : Wednesday 10th March 2021 to Thursday 8th April 2021 – Footway reconstruction works using localised traffic management in operation between 7.30am and 5.00pm.
Poppy Road, Princes Risborough – A4010 Wycombe Road to B4444 Station Road : Monday 15th March 2021 to Monday 19th April 2021 – Footway reconstruction works using footway closures and temporary traffic signals in operation between 7.30am and 5.00pm.