Roadworks for the week ahead – Monday 7th June 2021
Week commencing Monday 7th June 2021 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Conventional Surfacing Programme
Ledborough Lane, Beaconsfield – B474 Penn Road to A355 Amersham Road : Monday 7th June 2021 to Friday 11th June 2021 – Carriageway reconstruction works using a road closure in operation 24 / 7.
Surface Dressing Programme
Pink Road, Great Hampden – Peters Lane to Great Hampden : Monday 7th June 2021 to Tuesday 8th June 2021 – Surface dressing preparatory patching works using a road closure in operation between 7.30am and 4.30pm.
Small Dean Lane, Wendover – Wendover Bypass to Dunsmore Lane : Tuesday 8th June 2021 to Friday 11th June 2021 – Surface dressing preparatory patching works using a road closure in operation between 7.30am and 4.30pm.
Peterley Lane, Prestwood – Wycombe Road to Nairdwood Lane : Wednesday 9th June 2021 to Tuesday 15th June 2021 – Surface dressing preparatory patching works using a road closure in operation between 7.30am and 4.30pm.
Wood Lane, Iver – Five points roundabout to Langley Park Road : Monday 14th June 2021 to Friday 1st July 2021 – Surface dressing preparatory patching works using a road closure in operation between 7.30pm and 6.00am.
Nags Head Lane, Great Missenden – London Road to Nairdwood Lane : Wednesday 16th June 2021 to Thursday 24th June 2021 – Surface dressing preparatory patching works using a road closure in operation between 7.30am and 4.30pm.
Plane and Patch Programme
Ancillary works at various locations county wide prior to commencement of programme during week commencing 14th June 2021 : No carriageway incursion – works taking place between 9.30am and 3.30pm.
Micro Surfacing Programme
Ancillary works at various locations county wide prior to commencement of preparatory patching programme : No carriageway incursion – works taking place between 9.30am and 3.30pm.
Footway Improvement Programme
Ancillary works at various locations county wide prior to commencement of phase 2 footway improvement programme : No carriageway incursion – Works taking place between 9.30am and 3.30pm.
Drainage Improvement Programme
Chestnut Way, Longwick – Various locations along length of road : Monday 7th June 2021 to Friday 11th June 2021 – Drainage investigation works using temporary traffic signals and localised traffic management in operation between 7.30am and 4.30pm.
Ancillary works at various locations county wide prior to commencement of next schemes : No carriageway incursion – Works taking place between 9.30am and 3.30pm.
Intelligent Traffic Signals Improvement Works
Crest Road Signalisation, High Wycombe : Continuation of major works to convert existing roundabout on A4010, John Hall Way into a signalised junction with Crest Road. Completion anticipated early September.
Local Improvement Schemes
Booker Depot, High Wycombe : Monday 7th June 2021 to Friday 11th June 2021 – Surfacing work not on public highway, but using localised traffic management in operation between 7.30am and 4.30pm.
Great Missenden C of E School, Church Street, Great Missenden – Car park and turning head : Monday 7th June 2021 to Friday 6th August 2021 – Surfacing and lining works, not on highway but with localised traffic management in operation between 7.30am and 4.30pm.
*Source of information : Buckinghamshire Council.