Roadworks for the week ahead – Monday 30th August 2021
Week commencing Monday 30th August 2021 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
DfT Challenge Fund
A418, Aylesbury Road, Rowsham – Traffic lights north of Bierton to Wing : Tuesday 31st August 2021 to Sunday 5th September 2021 – Plane and Patch Resurfacing works to sections of the carriageway using a night time road closure in operation between 7.00pm and 6.00am.
Micro Surfacing Programme
Cherry Tree Road, Beaconsfield – Various location along length of road : Wednesday 1st September 2021 to Friday 3rd September 2021 – Kerbing and ancillary works using localised traffic management in operation between 7.00am and 7.00pm.
Footway Improvement Works
London End, Beaconsfield – Length of footway : Tuesday 31st August 2021 to Friday 24th September 2021 – Footway Improvement works using localised traffic management and 2 way temporary traffic signals in operation between 7.00am and 7.00pm.
Drainage Improvement Programme
Westbrook End, Newton Longville – Approximately 50m either side of bridge : Tuesday 31st August 2021 to Friday 3rd September 2021 – Drainage Improvement works using temporary traffic signals in operation between 7.00am and 6.00pm.
Junction Improvement Works
Crest Road, High Wycombe signalisation : Continuation of major works to convert the existing roundabout on A4010 John Hall Way into a signalised junction with Crest Road, with completion anticipated early September 2021.
*Source of information : Buckinghamshire Council.