Roadworks in Buckinghamshire for the week ahead – Monday 8th November 2021
Week commencing Monday 8th November 2021 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Conventional Surfacing Programme
A404 Amersham Hill, High Wycombe : Thursday 4th November 2021 to Friday 12th November 2021 – Surfacing works using a night time road closure in operation Monday to Friday between 8.00pm and 6.00am.
Glynswood Road, Buckingham : Monday 8th November 2021 to Tuesday 9th November 2021 – Surfacing works using a road closure in operation Monday to Friday between 8.00am and 6.00pm.
Plane and Patch Programme
Sheepcote Dell Road, Holmer Green : Tuesday 2nd November 2021 to Monday 8th November 2021 – Surface patching works using a road closure in operation Monday to Friday between 9.30am and 3.30pm.
Packhorse Road, Gerrards Cross : Monday 8th November 2021 – Surface patching works using a night time road closure in operation Monday to Friday between 8.00pm and 6.00am.
Dunton Road, Stewkley : Monday 8th November 2021 – Surface patching works using a road closure in operation Monday to Friday between 8.00am and 4.00pm.
Ballinger Road, Great Missenden : Tuesday 9th November 2021 to Thursday 11th November 2021 – Surface patching works using a road closure in operation Monday to Friday between 9.30am and 3.30pm.
Cock Lane, Tylers Green : Friday 12th November 2021 to Monday 15th November 2021 – Surface patching works using a road closure in operation Monday to Friday between 9.30am and 3.30pm.
A421 Finmere Tingewick Bypass : Saturday 13th November 2021 to Tuesday 16th November 2021 – Surface patching works using a night time road closure in operation 8.00pm and 6.00am.
Footway Improvement Works
Harvey Road, Aylesbury – From Mandeville Road to Barnard Crescent : Wednesday 3rd November 2021 to Monday 8th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.
Barnard Crescent, Aylesbury : Monday 8th November 2021 to Wednesday 10th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.
Grove Road, Amersham : Wednesday 10th November 2021 to Wednesday 17th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.
Fox Road, Holmer Green – From Harries Way to Browns Road : Friday 5th November 2021 to Friday 12th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.
Harries Way, Holmer Green : Tuesday 9th November 2021 to Monday 15th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.
Battings Wood Gardens, Naphill : Friday 12th November 2021 to Thursday 18th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.
Junction Improvement Works
A41 Bicester Road – Rabans Lane to Paradise Orchard including Jackson Road and Dickens Way, Aylesbury : Monday 20th September 2021 to June 2022 – Works will continue near to the Bicester Road junction with Sir Henry Lee Crescent / Paradise Orchard, on the North-West bound traffic lane 1. Works will involve excavation of the adjacent verge for the widening of the carriageway to create a new lane. Our works will include excavation for the installation of new kerbs, drainage and utility works, with a contraflow system setup to maintain 2-way traffic at all times. The working hours are Monday to Friday between 8.00am and 4.00pm.
Road Markings – Lining Refresh Scheme
A41 – Waddesdon to Bedgrove : Tuesday 26th October to Friday 19th November 2021 – Lining refreshment works using 2 / 3&4-way lights and lane closures in operation Monday to Friday between 9.00pm and 5.00am.
Bridge Schemes
High Street, Marlow – Marlow Bridge : Monday 4th October 2021 to Friday 4th February 2022 – Major bridge refurbishment using a footway closure when appropriate in operation Monday to Friday between 8.00am and 5.00pm.
Mill Lane, Taplow – Mill Lane Bridge : Monday 1st November 2021 to Friday 3rd December – Bridge demolition for Berry Hill Bridge; localised traffic management for site access point and compound area and a segregated area for pedestrians and cyclist movements. Monday to Friday between 8.00am and 4.00pm.
*Source of information : Buckinghamshire Council.