Roadworks in Buckinghamshire for the week ahead – Monday 20th December 2021

| December 17, 2021

Week commencing Monday 20th December 2021 Transport for Buckinghamshire will be carrying out work at the following locations.

The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.

Plane and Patch Programme

Vale Road, Chesham : Tuesday 30th November 2021 to Monday 20th December 2021 – Surfacing patching works using a road closure on 20th Decemeber 2021 in operation Monday to Friday between 7.00pm to 6.00am.

Blind Lane, Flackwell Heath – Woodside to Little Close : Wednesday 15th December 2021 to Wednesday 22nd December 2021 – Surfacing patching works using a three-way lights and a road closure in operation from 20th December 2021 to 22nd December 2021 in operation Monday to Friday between 8.00am and 5.00pm.

High Street, Chalfont St Peter : Thursday 16th December 2021 to Monday 20th December 2021 – Surfacing patching works using a road closure on 20thDecember 2021 in operation Monday to Friday between 8.00pm to 6.00am.

Chiltern Hill, Chalfont St Peter : Tuesday 21st December 2021 – Surfacing patching works using a road closure in operation Monday to Friday between 8.00pm to 6.00am.

Wycombe Road, Little Marlow : Wednesday 5th January 2022 to Friday 7th January 2022 – Surfacing patching works using a road closure in operation Monday to Friday between 8.00am and 5.00pm.

Footway Improvement Works

Ambleside, Aylesbury – Cambourne Avenue to Hambledon Close : Monday 15th November 2021 to 23rd December 2021 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 8.00am and 4.00pm.

Buckingham Road, Aylesbury – New Street Roundabout to Selkirk Avenue : Monday 13th December 2021 to Friday 14th January 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 9.30am and 3.30pm.

High Street, Aylesbury : Tuesday 4th January 2022 to Wednesday 2nd February 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 8.00am and 6.00pm.

Junction Improvement Works

A41 Bicester Road – Rabans Lane to Paradise Orchard including Jackson Road and Dickens Way, Aylesbury : Monday 20th September 2021 to June 2022 – Works will continue near to the Bicester Road junction with Sir Henry Lee Crescent / Paradise Orchard, on the North-West bound traffic lane. Week commencing Monday 20th December 2021, works will include final installation of new drainage, construction of new footway and general site tidying. There will be lane closures on each approach to the Jackson Road / Dickens Way roundabout which are in operation 24 hours a day and a two-way traffic flow will be maintained whilst the lane closures are in place. There will also be a Contraflow system (24hrs a day) on Bicester Road between Stone Bridge and the junction with Paradise Orchard / Sir Henry Lee Crescent from Monday 1st November 2021 to allow for construction of left turn lane.

Bridge Schemes

High Street, Marlow – Marlow Bridge : Monday 4th October 2021 to Friday 4th February 2022 – Major bridge refurbishment using a footway closure when appropriate in operation Monday to Friday between 8.00am and 5.00pm.

Mill Lane, Taplow – Mill Lane Bridge : Monday 1st November 2021 to Friday 24th December 2021 – Bridge demolition for Berry Hill Bridge; localised traffic management for site access point and compound area and a segregated area for pedestrians and cyclist movements. Monday to Friday between 7.00am and 7.00pm.

*Source of information : Buckinghamshire Council.