Week commencing Monday 10th January 2022 Transport for Buckinghamshire will be carrying out work at the following locations.

The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.

Plane and Patch Programme

Gordon Road and Bowerdean Road, High Wycombe – Princes Gate to Chichester Close : Monday 10th January 2022 to Tuesday 11th January 2022 – Surfacing patching works using a road closure in operation Monday to Friday between 8.00am and 7.00pm.

Totteridge Road, High Wycombe – Amersham Hill to Queen Street : Wednesday 12th January 2022 to Thursday 13th January 2022 – Surfacing patching works using a road closure in operation Monday to Friday between 8.00am and 7.00pm.

Copners Drive, Holmer Green – Browns Road to Skimmers Field : Monday 10th January 2022 to Wednesday 12th January 2022 – Surfacing patching works using a road closure in operation Monday to Friday between 8.00am and 5.00pm.

Skimmers Field, Holmer Green – Orchard Way to Bramble Crescent : Thursday 13th January 2022 to Friday 14th January 2022 – Surfacing patching works using a road closure in operation Monday to Friday between 8.00am and 5.00pm.

Footway Improvement Works

Ambleside, Aylesbury – Cambourne Avenue to Hambledon Close : Monday 15th November 2021 to Friday 7th January 2022 – (These works have overrun as a result of COVID-19) Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 8.00am and 6.00pm.

Buckingham Road, Aylesbury – New Street Roundabout to Selkirk Avenue : Monday 13th December 2021 to Friday 14th January 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 8.00am and 6.00pm.

High Street, Aylesbury : Tuesday 4th January 2022 to Wednesday 2nd February 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 9.00am and 4.00pm.

Wycombe Road, Saunderton – Lee Road to Culverton Crossroads : Monday 10th January 2022 to Tuesday 25th January 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 8.00am and 6.00pm.

Junction Improvement Works

A41 Bicester Road – Rabans Lane to Paradise Orchard including Jackson Road and Dickens Way, Aylesbury : Monday 20th September 2021 to June 2022 – Week commencing Monday 10th January 2022, works will commence on A41 Bicester Road at Stone Bridge to undertake carriageway widening and the installation of a new central refuge island. 2-way temporary traffic lights will be in place from 9.30am to 3.30pm with narrow lanes used outside of these hours.

Drainage Improvement Works

Hampden Road, Great Hampden – From the crossroads to Pink Road : Monday 10th January 2022 to Tuesday 18th January 2022 – Drainage improvement works using a road closure in operation Monday to Friday between 8.00am and 5.00pm.

Bridge Schemes

High Street, Marlow – Marlow Bridge : Monday 4th October 2021 to Friday 4th February 2022 – Major bridge refurbishment using a footway closure when appropriate in operation Monday to Friday between 8.00am and 5.00pm.

*Source of information : Buckinghamshire Council.