Roadworks in Buckinghamshire for the week ahead – Monday 7th February 2022
Week commencing Monday 7th February 2022 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Conventional Surfacing Programme
Slough Road, Iver : Monday 7th February 2022 to Sunday 20th February 2022 – Surfacing works using a road closure in operation Monday to Sunday between 7.30am and 5.00pm.
Plane and Patch Programme
Bottom Lane, Seer Green : Monday 7th February 2022 to Friday 11th February 2022 – Surfacing patching works using a road closure in operation Monday to Friday between 7.30am and 5.00pm.
Ellesborough Road, Wendover : Monday 7th February 2022 to Thursday 17th February 2022 – Surfacing patching works using a road closure in operation Monday to Friday between 9.30am and 3.30pm.
Buckingham Ring Road East, Buckingham : Monday 7th February 2022 to Friday 18th February 2022 – Surfacing patching works using a road closure in operation Monday to Friday between 8.00pm and 6.00am.
Footway Improvement Works
Grove Road, Amersham – From Roundwood Road to Quill Hall Lane : Monday 15th November 2021 to Monday 14th February 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 8.00am and 6.00pm.
Wycombe Road, Saunderton – Lee Road to Woodway : Monday 10th January 2022 to Tuesday 25th February 2022 – Footway improvement works using a footway closure and two-way temporary traffic lights in operation Monday to Friday between 9.30am and 3.30pm.
Marsham Way, Gerrards Cross – From Mill Lane to Packhorse Road : Friday 19th November 2021 to Thursday 10th February 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 8.00am and 6.00pm.
Dropmore Road, Burnham – From High Street to Poyle Lane : Friday 17th January 2022 to Monday 7th February 2022 – Footway preparation works using a footway closure and three-way temporary traffic lights in operation Monday to Friday between 9.00am and 3.00pm.
High Street, Aylesbury – Britannia Street to Market Square : Monday 17th January 2022 to Wednesday 16th February 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 7.00am and 7.00pm.
Wycombe End, Beaconsfield – Holtspur Top Lane to Old Bengal Restaurant : Monday 17th January 2022 to Tuesday 1st March 2022 – Footway improvement works using a footway closure and give and three-way temporary traffic lights in operation Monday to Friday between 9.30am and 3.30pm.
Lucas Road, High Wycombe – From A404 to Totteridge Road : Monday 31st January 2022 to Wednesday 16th February 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 8.00am and 6.00pm.
Welbeck Avenue, Aylesbury – From Ingram Avenue to Bedgrove : Thursday 10th February 2022 to Wednesday 9th March 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 8.00am and 6.00pm.
Drainage Improvement Works
Middle Close, Amersham : Monday 7th February 2022 to Friday 11th February 2022 – Drainage improvement works using a road closure in operation Monday to Friday between 8.00am and 5.00pm.
Gorelands Lane, Chalfont St Giles – From Deadhearn Lane to Chesham Lane : Monday 7th February 2022 to Wednesday 2nd March 2022 – Drainage improvement works using a road closure in operation Monday to Friday between 8.00am and 5.00pm.
Network Improvement Schemes
A413 Padbury : Buckingham Road – From Springfields to Old Springfields : Monday 24th January 2022 to Friday 11th February 2022 – Installation of toucan pedestrian crossing using 24-hour two-way temporary traffic lights including weekends.
A404 Marlow Culvert – Parkway : Friday 4th February 2022 to Monday 7th February 2022 – Surface water jetting investigation of culvert using two-way temporary traffic lights in operation Friday to Monday between 7.30pm and 6.00am.
Lining works
A421 – From Tingewick roundabout to the roundabout of A421 and A413 : Monday 17th January 2022 to Friday 11th February 2022 – Lining works using two-way temporary traffic lights in operation Monday to Friday between 9.30am and 3.30pm and night works between 7.30pm and 7.00am.
West Street, Steeple Claydon : Monday 24th January 2022 to Friday 4th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 8.00am and 5.00pm.
Main Street, Grendon Underwood : Monday 24th January 2022 to Friday 4th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 8.00am and 5.00pm.
Bowler Road, Aylesbury – From Churchill Avenue to Rake Way : Monday 24th January 2022 to Friday 4th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 8.00am and 5.00pm.
Brook End, Weston Turville – From Aerodrome Road to New Street : Monday 24th January 2022 to Friday 4th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
New Road, Weston Turville – From the Holiday Inn to Main Street : Monday 24th January 2022 to Friday 4th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Thornborough Road, Thornborough / Padbury Road, Padbury – From A413 Buckingham Road to A421 Bletchey Road : Monday 24th January 2022 to Monday 28th February 2022 – Lining works using 2 / 3-way temporary traffic lights in operation Monday to Friday between 9.30am and 3.30pm.
Whaddon Road / Mursley Road, Mursley – From A421 Bletchley Road to Main Station Road junction : Monday 24th January 2022 to Monday 28th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Cublington Road, Cublinton / Wing Road, Wing : Monday 24th January 2022 to Monday 28th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Pound Hill / Green End, Great Brickhill – From Lower Way junction to near Home Farm Lane : Monday 24th January 2022 to Monday 28th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
B489 Tring Road, Edlesborough – From Chapel Lane to the junction with B440 Leighton Road : Monday 24th January 2022 to Monday 28th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
B489 Dunstable Road, Ivinghoe – From Chapel Lane to the junction with B488 : Monday 24th January 2022 to Monday 28th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
B489 Lower Ickneild Way, Marsworth – From the junction with Watery Lane to Marsworth Village : Monday 24th January 2022 to Monday 28th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Weston Road, Aston Clinton – From London Road to Aerodrome Road : Monday 24th January 2022 to Friday 4th February 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Latimer Road / Latimer Village, Latimer – From Bell Lane to the junction with A404 : Monday 24th February 2022 to Friday 18th March 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Marlow Road, Stokenchurch – From A40 to Bigmore Lane : Monday 24th February 2022 to Friday 18th March 2022 – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Amersham Road (A404), Little Chalfont : Monday 24th February 2022 to Friday 18th March – Lining works using stop and go traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Bridge Schemes
High Street, Marlow – Marlow Bridge : Monday 4 October 2021 to Tuesday 25 October 2022 – Major bridge refurbishment using a footway closure when appropriate in operation Monday to Friday between 8.00am and 5.00pm.
Highway Infrastructure Projects (HIPs)
A41 Bicester Road – Rabans Lane to Paradise Orchard including Jackson Road and Dickens Way, Aylesbury : Tuesday 1st June 2021 to 30th June 2022 – Works will continue on A41 Bicester Road at Stone Bridge, with footway works being undertaken. This will include excavation of footway, installation of new edgings and new kerbs. This phase of works will take approximately 2 weeks, to be completed under narrow lane closures on West-bound traffic.
*Source of information : Buckinghamshire Council.