‘Failed Road’ Schemes
Chardon to Marsh Gibbon : Thursday 5th January 2023 to Wednesday 11th January 2023 – Resurfacing works using recycled material using give and take traffic management in operation Monday to Friday between 8.00am and 5.00pm.
Heet Road, Marsh Gibbon : Thursday 5th January 2023 to Wednesday 11th January 2023 – Resurfacing works using recycled material using give and take traffic management in operation Monday to Friday between 8.00am and 5.00pm.
Marsh Gibbon to Edgcott : Thursday 5th January 2023 to Wednesday 11th January 2023 – Resurfacing works using recycled material using give and take traffic management in operation Monday to Friday between 8.00am and 5.00pm.
Shipton Lee, Edgcott : Thursday 5th January 2023 to Wednesday 11th January 2023 – Resurfacing works using recycled material using give and take traffic management in operation Monday to Friday between 8.00am and 5.00pm.
Footway Improvement Works
Broughton Avenue, Aylesbury – From Richmond Road to Parton Road : Monday 17th October 2022 to Tuesday 31st January 2023 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Yarrowside, Little Chalfont : Tuesday 13th December 2022 to Tuesday 10th January 2023 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 8.00am and 5.00pm.