Roadworks in Buckinghamshire for the week ahead – Monday 23rd January 2023

| January 20, 2023

Week commencing Monday 23rd January 2023 roadworks are scheduled to take place at the following locations in Buckinghamshire.

The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.

‘Failed Road’ Schemes

Risborough Road, Aston Sandford : Monday 16th January 2023 to Thursday 26th January 2023 – Resurfacing works using recycled material using a road closure in operation between 8.00am and 5.30pm with the closure in place overnight and weekends.

Conventional Surfacing Works

Stewkley Road, Cublington : Monday 23rd January 2023 to Wednesday 1st February 2023 – Resurfacing works using recycled material using a road closure in operation between 8.00am and 5.30pm with the closure in place overnight and weekends.

Studley Road, Cublington : Friday 27th January 2023 to Friday 3rd February 2023 – Resurfacing works using recycled material using a road closure in operation between 8.00am and 5.30pm with the closure in place overnight and weekends.

Footway Improvement Works

Broughton Avenue, Aylesbury – From Richmond Road to Parton Road : Monday 17th October 2022 to Tuesday 31st January 2023 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 9.30am and 3.30pm.

Vicarage Lane, Steeple Claydon : Monday 9th January 2023 to Friday 3rd February 2023 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 8.00am and 5.00pm.

Community Board Works

Blackpond Lane, High Wycombe – From Seren Place to Hawthorn Lane : Monday 9th January 2023 to Friday 3rd February 2023 – Installing a new footway using give and take traffic management in operation Monday to Friday between 8.00am and 5.00pm.

Hillview Road, High Wycombe : Monday 23rd January 2023 to Friday 27th January 2023 – Installing bollards on the triangle grass verge island using give and take traffic management in operation Monday to Friday between 9.30am to 3.30pm.

Ambleside, Aylesbury : Monday 23rd January 2023 to Tuesday 31st January 2023 – Installing dropped kerbs using give and take traffic management in operation Monday to Friday between 9.30am to 3.30pm.

Network Safety Works

Woodside Road / Chiltern Avenue, Amersham : Monday 23rd January 2023 to Friday 3rd February 2023 – Upgrading pedestrian crossing point, installing new signage and lining works using three-way temporary traffic lights in operation Monday to Friday between 9.30am and 3.30pm.

New Street, Aylesbury – From A413 Buckingham Road to Lucky Lane : Monday 23rd January 2023 to Wednesday 25th January 2023 – High friction surfacing and lining works using a lane closure in operation Monday to Friday between 8.00pm and 6.00am.

Safety Barrier Repair Works

A41 Bicester Road, Grendon Underwood – With the junction of The Broadway : Monday 23rd January 2023 to Friday 17th February 2023 – Safety barrier repair works using three-way temporary traffic lights in operation Monday to Friday between 9.30am and 3.30pm.

Highway Infrastructure Projects (HIPs)

A41 Bicester Road – Rabans Lane to Paradise Orchard including Jackson Road and Dickens Way, Aylesbury : From Monday 9th January 2023 until Monday 27th February 2023, TfB will be carrying out drainage works, replacing traffic signs and defect repairs, using lane incursions in operation Monday to Friday between 8.00am and 4.00pm.

*Source of information : Press release from Buckinghamshire Council.