During the past week Transport for Buckinghamshire (Tfb) crews attended to nearly 500 potholes and over 1600 drains have been cleared using gully emptying vehicles.
In addition to routine and reactive maintenance, TfB programmes continued including the LED street light replacement programme and road patching programme.
Since the LED street light replacement programme began 1639 traditional street light lanterns have been replaces with more modern, efficient LED lamps. The replacement programme is now 63% complete and on track to complete by March 2015.
The TfB road patching programme has now visited 74 sites, which accounts for 56% of the total project. TfB are on track to complete to schedule, in March 2015.
TfB are currently meeting with Buckinghamshire County Councillors to see which roads they would like included in our larger scale treatment programme, starting in the Spring. A full list is being put together and will be available soon.
In the coming week the street light replacement programme continues in the following locations:
Bletchley Road, Whaddon : Continues 16th February 2015, 10.00am-2.00pm. Traffic lights
Oxford Road, Stone : Continues 16th February 2015, 10.00am-14.30, Stop/go
Tring Road, Edlesborough : Continues 16th & 17th February 2015, 9.00am-4.00pm. Traffic lights
Aylesbury Road, Waddesdon : Continues 16th & 17th February 2015, 10.00am-2.00pm. Traffic lights
Mursley Road, Swanbourne : Continues 16th & 17th February 2015, 9.30am-4.30pm. Traffic lights
Coddimoor Lane, Whaddon : Continues 16th & 17th February 2015, no time restrictions. Traffic lights
Upper Icknield Way, Pitstone : 16th-18th February 2015,9.00am-3.00pm, Traffic lights
Haydon Road, Aylesbury : 16th-18th February 2015, 10.00am-2.00pm. Stop/go
High Street, Waddesdon : 16th-18th February 2015, 10.00am-3.00pm. Stop/go
Wendover Bypass, Wendover : 17th-19th February 2015, 9.30am-4.30pm. Traffic lights
Denham Road, Denham : 18th-20th February 2015, 9.00am-5.00pm. Traffic lights
High Street, Whitchurch : 19th-23rd February 2015, 9.00am-5.00pm. Stop/go
Market Square, Buckingham : 19th-23rd February 2015, 09.00-4.00pm. Stop/go
Bridge Street, Buckingham : 19th-23rd February 2015, No time restrictions. Stop/go
Station Approach, Amersham : 20th-24th February 2015, 9.30am-2.30pm. Stop/go
Tingewick Road, Radclive : 20th-24th February 2015, 10.00am-2.00pm. Traffic lights
There may be day time restrictions in place during these dates.
The TfB road patching work also continues in the following locations:
Trinity Road, Marlow : Monday 16th February 2015 – Tuesday 17th February 2015
Wethered Road, Marlow : Monday 16th February 2015 – Tuesday 17th February 2015
Mayflower Way, Farnham Common : Monday 16th February 2015 – Wednesday 18th February 2015
Rectory Road, Taplow : Wednesday 18th February 2015
Galley Lane, Great Brickhill : Wednesday 18th February 2015
Thame Road, Brill : Wednesday 18th February 2015 – Thursday 19th February 2015
Lynton Road, Chesham : Thursday 19th February 2015
Main Street, Gawcott : Thursday 19th February 2015 – Friday 20th February 2015
Hawridge Common, Hawridge : Friday 20th February 2015
Edgcott Road, Grendon Underwood : Sunday 22nd February 2015
All the above are daytime patching works being carried out utilising a road closure.
Whitefield Lane, Great Missenden : Friday 20th February 2015
The above is a daytime patching work being carried out utilising traffic lights.
Orchard End Avenue, Amersham : Thursday 19th February 2015 – Friday 20th February 2015
School Lane, Dinton : Friday 20th February 2015
All the above are daytime patching works being carried out utilising give and take traffic management.