During the past week Transport for Buckinghamshire (TfB) workers repaired 746 potholes and cleared 1683 gullies.
The TfB road patching programme is now 75% complete. Over the next week the programme will continue at the following locations :
Edgcott Road – Grendon Underwood : Sunday 8th March 2015
These are daytime patching works being carried out utilising a road closure
Perks Lane – Prestwood : Ongoing – Monday 9th March 2015
These are daytime patching works being carried out utilising a road closure
Fulmer Drive – Gerrards Cross : Ongoing – Wednesday 11th March 2015
These are daytime patching works being carried out utilising give and take TM
Burford Close – Marlow Bottom : Tuesday 10th March 2015
These are daytime patching works being carried out utilising give and take TM
Singleborough Lane – Singleborough : Tuesday 10th March 2015
These are daytime patching works being carried out utilising a road closure
Burnham Close – Bourne End : Wednesday 11th March 2015
These are daytime patching works being carried out utilising give and take TM
College Farm Rd – Hillesden : Wednesday 11th March 2015
These are daytime patching works being carried out utilising a road closure
Chalkpit Lane – Marlow : Thursday 12th March 2015
These are daytime patching works being carried out utilising an offpeak road closure
Monkton Way – Speen : Thursday 12th March 2015
These are daytime patching works being carried out utilising give and take TM
Aylesbury Rd – Swanbourne : Thurdsay 12th March 2015
These are night time patching works being carried out utilising a road closure
Abbottswood – Speen : Friday 13th March 2015
These are daytime patching works being carried out utilising give and take TM
New Road – High Wycombe : Friday 13th March 2015 – Monday 16th March 2015
These are daytime patching works being carried out utilising off peak 2 way traffic lights
Fieldhouse Lane – Marlow : Saturday 14th March 2015 – Sunday 15th March 2015
These are daytime patching works being carried out utilising off-peak 3 way traffic lights
Next week TfB start a High Friction Surfacing programme. The work is extremely weather dependent, however over the coming week TfB are planning to be in the following locations:
Cores End Road, Bourne End : Works at the crossing between Highfield Road and New Road : Wednesday 11 March 2015
These are night-time works being carried out utilising temporary traffic lights
Latimer Road & Stony Lane, Chenies : Works at Latimer Road junction with Stony Lane : Friday 13 March 2015