Road surfacing works week commencing 24th Oct 2016

| October 23, 2016

HighStreet-HighWycombe-TfB-2014-11-13-SDC11523

Week commencing Monday 24th October 2016 Transport for Buckinghamshire will be carrying out work at the following locations.

The dates shown are subject to change at short notice.

Conventional Surfacing Programme

Woodside Ave, Chesham Bois : Monday 24th October 2016 to Friday 28th October 2016 – Daytime surfacing work and the reinstatement of road markings using a daytime road closure between 7.00am and 7.00pm.

Gibson Lane, Haddenham : Friday 28th October 2016 to Monday 31st October 2016 – Daytime surfacing work and the reinstatement of road markings using a daytime road closure between 7.00am and 7.00pm.

Micro-surfacing Programme

Micro-surfacing

Woodland Close, High Wycombe : Saturday 22nd October 2016 to Sunday 23rd October 2016 – Daytime micro-surfacing treatment using a daytime road closure between 8.00pm and 5.00pm.

Little Hivings, Chesham : Monday 24th October 2016 – Daytime micro-surfacing treatment using a daytime road closure between 8.00pm and 5.00pm.

Beaumont Way (spur roads), Hazlemere : Monday 24th October 2016 to Wednesday 26th October 2016 – Daytime micro-surfacing treatment using a daytime road closure between 09:00 and 5.00pm.

Broadview Road, Chesham : Tuesday 25th October 2016 to Wednesday 26th October 2016 – Daytime micro-surfacing treatment using a daytime road closure between 8.00pm and 5.00pm.

Ironwork Adjustments

Hill Close, Wooburn Green : Saturday 22nd October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Farm Lea, Wooburn Green : Saturday 22nd October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Cambridge Road, Beaconsfield : Saturday 22nd October 2016 to Sunday 23rd October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Beechwood Road, Beaconsfield : Saturday 22nd October 2016 to Wednesday 26th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

South Park Crescent, Gerrards Cross : Sunday 23rd October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Munces Road, Marlow Bottom : Monday 24th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Meadow View, Marlow Bottom : Monday 24th October 2016 to Tuesday 25th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Holman Street, Aylesbury : Monday 24th October 2016 to Tuesday 25th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Well Street, Buckingham : Monday 24th October 2016 to Thursday 27th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Combe Rise, Sands : Monday 24th October 2016 to Thursday 27th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Chantry Road, Aylesbury : Tuesday 25th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

St Peters Avenue, Aylesbury : Tuesday 25th October 2016 to Wednesday 26th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Deeds Grove Spur Road, High Wycombe : Wednesday 26th October 2016 to Thursday 27th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Church Street, Buckingham : Thursday 27th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Lansdell Ave, High Wycombe : Thursday 27th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Berryfield Road, Aylesbury : Thursday 27th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Argyle Ave, Aylesbury : Thursday 27th October 2016 to Friday 28th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Totteridge Drive and Service Road, High Wycombe : Thursday 27th October 2016 to Friday 28th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Curlew Close, Downley : Thursday 27th October 2016 to Friday 28th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Fulton Close, Downley : Friday 28th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Elm Street, Buckingham : Friday 28th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

St Rumbolds Lane, Buckingham : Friday 28th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Spearing Road, High Wycombe : Friday 28th October 2016 to Wednesday 2nd November 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Manor Street, Buckingham : Saturday 29th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Lavender Close, Aylesbury : Saturday 29th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Bayley Gardens, Naphill : Saturday 29th October 2016 to Monday 31st October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Ford Street, Buckingham : Saturday 29th October 2016 to Sunday 30th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Cyclamen Place, Aylesbury : Sunday 30th October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Lupin Walk, Aylesbury : Sunday 30th October 2016 to Monday 31st October 2016 – Daytime ironwork adjustments using temporary traffic signals/Stop and Go traffic management between 7.00am and 7.00pm.

Reinstatement of Road Markings and Road Studs

Various Locations Reinstatement of road markings and road studs ongoing.

Plane and Patch Programme

Turnfurlong Lane, Aylesbury : Monday 24th October 2016 to Tuesday 25th October 2016 – Daytime targeted patching work using a daytime road closure between 7.00am and 7.00pm.

Village Road, Little Missenden : Tuesday 25th October 2016 to Wednesday 26th October 2016 – Daytime targeted patching work using a daytime road closure between 7.00am and 7.00pm.

Barnards Hill, Marlow : Wednesday 26th October 2016 – Daytime targeted patching work using a daytime road closure between 7.00am and 7.00pm.

Fowler Road, Aylesbury : Thursday 27th October 2016 to Friday 28th October 2016 – Night time targeted patching work using a night time road closure between 7.00pm and 6.00am.

Ellen Road, Aylesbury : Friday 28th October 2016 – Night time targeted patching work using a night time road closure between 7.00pm and 6.00am.