Road surfacing works week commencing 11th Dec 2017

Road repairs: a ‘plane and patch’ team resurface a small section of road.
Week commencing Monday 11th December 2017 Transport for Buckinghamshire will be carrying out work at the following locations.
The work is weather dependent therefore the dates shown are subject to change at short notice.
Carriageway Surfacing Schemes
Addington Estate Road, Addington – A413 Buckingham Road to Verney Road : Monday 11th December 2017 – Resurfacing works using a road closure between 7.30am and 6.00pm.
Main St, Radclive : Tuesday 12th December 2017 – Resurfacing remedial works using temporary traffic signals between 9.30am and 3.30pm.
The Barracks, Hillesden : Tuesday 12th December 2017 – Resurfacing remedial works using temporary traffic signals between 9.30am and 3.30pm.
Chestnut Way, Longwick : Wednesday 13th December 2017 – Resurfacing remedial works using a day time road closure between 9.30am and 3.30pm.
Whielden Lane, Winchmore Hill – A404 to Nelson Close : Monday 11th December 2017 – Ironwork adjustments : remedial work – using a day time road closure from 7.30am and 4.00pm.
Grange Way & Dutton Way, Iver – Whole length of road : Monday 11th December 2017 to Tuesday 12th December 2017 – Ironwork adjustments using localised traffic management from 8.00am and 4.00pm.
River Road & Ellington Road, Taplow – A4 to River Road junction : Monday 11th December 2017 to Wednesday 13th December 2017 – Ironwork adjustments using localised traffic management from 8.00am and 4.00pm.
High Street, Haddenham – Whole length of road : Thursday 14th December 2017 – Ironwork adjustments : remedial work – using localised traffic management from 8.00am and 4.00pm.
Addington Road, Buckingham – A413 to A422 : Thursday 14th December 2017 – Ironwork adjustments : remedial work – using a day time road closure from 7.30am and 4.00pm.
Hollow Way Lane, Chesham Bois – Latimer Road to Bois Lane : Friday 15th December 2017 – Ironwork adjustments : remedial work – using a day time road closure from 7.30am and 4.00pm.
Fulmer Road, Gerrards Cross – Junction with Fulmer Drive : Friday 15th December 2017 – Ironwork adjustments : remedial work – using temporary traffic signals from 9.00am and 3.00pm.
Footway Surfacing Schemes
Stratford Road, Nash – Hollywell Cottages to Hollywell Bungalows : Monday 11th December 2017 – Daytime footway resurfacing works using multi way signals between 7.30am and 4.30pm.
Howard Avenue, Aylesbury – Northumberland Avenue to Long Meadow : Monday 11th December 2017 to Friday 22nd December 2017 – Daytime footway resurfacing works using localised traffic management between 7.30am and 4.30pm.
Westmorland Avenue, Aylesbury – Turnfurlong Lane to Howard Avenue : Monday 11th December 2017 to Friday 22nd December 2017 – Daytime footway resurfacing works using localised traffic management between 7.30am and 4.30pm.
Greenway, Chesham – Upper Belmont Road to Little Spring : Monday 11th December 2017 to Wednesday 20th December 2017 – Daytime footway resurfacing works using multi way signals between 9.30am and 3.30pm.
Beel Close, Little Chalfont – White Lion Road to Cul-De-Sac : Monday 11th December 2017 to Friday 22nd December 2017 – Daytime footway resurfacing works using localised traffic management between 7.30am and 4.30pm.
Piggotts Orchard, Amersham – A355 to Cul-De-Sac : Tuesday 12th December 2017 to Monday 18th December 2017 – Daytime footway resurfacing works using localised traffic management between 7.30am and 4.30pm.
Drainage Programme
Foundry Lane/Loosely Hill, Loosley Row : Monday 11th December 2017 to Wednesday 13th December 2017 – Daytime drainage improvements using a road closure between 9.30am and 3.30pm.