Road surfacing works week commencing 22nd Jan 2018
Week commencing Monday 22nd January 2018 Transport for Buckinghamshire will be carrying out work at the following locations.
The work is weather dependent therefore the dates shown are subject to change at short notice.
Footway Surfacing Schemes
Westmorland Avenue, Aylesbury – Turnfurlong Lane to Howard Avenue : Monday 22nd January 2018 – Daytime footway resurfacing works using localised traffic management between 7.30am and 4.30pm.
Woodstock Close, Aylesbury – Whole length of road : Monday 22nd January 2018 to Friday 26th January 2018 – Daytime footway resurfacing works using localised traffic management between 7.30am and 4.30pm.
Woodside Road, Amersham – Chiltern Avenue to Sycamore Road : Monday 22nd January 2018 to Friday 2nd February 2018 – Daytime footway resurfacing works using multi way signals between 9.30am and 3.30pm.
Bathurst Walk, Iver – Thorney Lane South to Wellesley Ave : Monday 22nd January 2018 to Friday 2nd February 2018 – Daytime footway resurfacing works using two way signals between 9.30am and 3.30pm.
Shortborough Avenue, Princes Risborough – Wellington Avenue to Westmead : Monday 22nd January 2018 to Tuesday 6th February 2018 – Daytime footway resurfacing works using localised traffic management between 7.30am and 4.30pm.
Parton Road, Aylesbury : Monday 22nd January 2018 to Friday 9th February 2018 – Daytime footway resurfacing works using localised traffic management between 9.30am and 3.30pm.
Windermere Close, Aylesbury – Whole length of road : Tuesday 23rd January 2018 to Tuesday 30th January 2018 – Daytime footway resurfacing works using localised traffic management between 7.30am and 4.30pm.
Drainage Schemes
Church Lane, Little Horwood – Shucklow Hill to Mursley Road : Monday 22nd January 2018 – Friday 26th January 2018 – Daytime drainage works using a road closure between 8.00am and 4.00pm.