Week commencing Monday 3rd September 2018 Transport for Buckinghamshire will be carrying out work at the following locations.

The work is weather dependent therefore the dates shown are subject to change at short notice.

Resurfacing Programme

A4146 Stoke Hammond Bypass – A418 Wing Road roundabout to A4146 Willowbridge roundabout : Monday 13th August 2018 to Sunday 7th October 2018 –  Resurfacing works taking place using various closures.

  • Resurfacing works taking place using a 24 hour road closure of the northbound (towards Milton Keynes) carriageway from Monday 3rd September 2018 to Sunday 9th September 2018 – Changeover of traffic management and transfer of plant/equipment to southbound (towards Wing) carriageway using a 24 hour closure of the complete bypass from 7.00pm on the 09/09/2018 to 6.00am on Monday 10th September 2018.
  • Resurfacing works taking place using a 24 hour road closure of the southbound (towards Wing) carriageway from Monday 10th September 2018 to Sunday 7th October 2018 – Bypass reopens completely on Sunday 7th October 2018. Further detailed updates to follow during the course of the works.

A4146 Stoke Hammond Bypass – A418 Wing Road roundabout to A4146 Willowbridge roundabout :

  • Monday 3rd September 2018 to Sunday 7th October 2018 – Resurfacing works taking place using a 24 hour road closure of the northbound (towards Milton Keynes) carriageway from Monday 3rd September 2018 to Sunday 9th September 2018.
  • Changeover of traffic management and transfer of plant/equipment to southbound (towards Wing) carriageway using a 24 hour closure of the complete bypass from 7.00pm on the Sunday 9th September 2018 to 6.00am on the Monday 10th September 2018.

Elmhurst Road, Aylesbury – Whole length of road : Monday 3rd September 2018 – Conventional Surfacing works taking place using a night time road closure between 7.00pm and 6.00am.

Addington Estate Road, Addington – Whole length of road : Monday 3rd September 2018 to Friday 7th September 2018 – Conventional Surfacing works taking place using a day time road closure between 7.00am and 7.00pm.

Amersham Road, Beaconsfield – Ledborough Lane to Layby at top of the hill : Tuesday 4th September 2018 to Monday 10th September 2018 – Conventional Surfacing works taking place using a night time road closure between 7.00pm and 6.00am.

Beaconsfield Road/Milton Road/Roseberry Road/Beechwood Way, Aston Clinton – Whole length of road : Monday 3rd September 2018 to Wednesday 5th September 2018 – Micro-surfacing works taking place using a day time road closure between 7.00am and 7.00pm.

Plantation Road, Amersham – Whole length of road : Wednesday 5th September 2018 to Thursday 6th September 2018 – Micro-surfacing remedial works taking place using a day time road closure between 7.00am and 7.00pm.

Lionel Avenue, Wendover – Aylesbury Road to Dobbins Lane : Thursday 6th September 2018 to Monday 10th September 2018 – Micro-surfacing works taking place using a day time road closure between 7.00am and 7.00pm.

Bathurst Walk, Iver – Whole length of road : Monday 3rd September 2018 to Tuesday 4th September 2018 – Micro-surfacing works taking place using a day time road closure between 7.00am and 7.00pm.

Addison Close, Iver – Whole length of road : Tuesday 4th September 2018 – Micro-surfacing remedial works taking place using localised traffic management between 7.00am and 7.00pm.

Windsor Road, Gerrards Cross – Whole length of road : Tuesday 4th September 2018 to Thursday 6th September 2018 – Micro-surfacing remedial works taking place using a day time road closure between 9.30am and 3.30pm.

Fulmer Road / Windmill Hill, Fulmer – Whole length of road : Thursday 6th September 2018 to Tuesday 11th September 2018 – Micro-surfacing works taking place using a day time road closure between 9.30am and 3.30pm.

Latimer Road, Chesham – Whole length of road : Monday 3rd September 2018 to Friday 7th September 2018 – Ironwork remedials taking place using two way signals between 9.30am and 3.30pm.

Great Lane and side roads, Bierton – Whole length of road : Tuesday 4th September 2018 – Ironwork remedials taking place using localised traffic management between 7.00am and 7.00pm.

Prebendal Avenue, Aylesbury – Whole length of road : Tuesday 4th September 2018 to Friday 7th September 2018 – Ironwork remedials taking place using localised traffic management between 7.00am and 7.00pm.

Drainage Programme

A4 Bath Road, Taplow – Junction Hag Hill Lane : Monday 3rd September 2018 to Wednesday 5th September 2018 – Drainage works taking place using multi way signals between 9.30am and 3.30pm.

Haw Lane, Saunderton – Outside No.49 : Monday 3rd September 2018 to Tuesday 11th September 2018 – Drainage works taking place using localised traffic management between 8.00am and 5.00pm.

Bryants Bottom, Great Missenden – From Beachgrove to Hampden Road : Monday 3rd September 2018 to Monday 17th September 2018 – Drainage works taking place using localised traffic management between 8.00am and 5.00pm.