Roadworks for the week ahead – Mon 22nd Apr 2019
Week commencing Monday 22nd April 2019 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme and, as some activities are weather dependent, dates may change at short notice.
Carriageway surfacing
Church Road / Slapton Lane, Slapton – B440 to Church Access Road : Tuesday 23rd April 2019 to Thursday 2nd May 2019 – Conventional resurfacing taking place using a day time road closure between 7.00am and 7.00pm.
Heath Road, Beaconsfield – Whole length of road : Tuesday 23rd April 2019 to Thursday 25th April 2019 – Micro surfacing prep works taking place using a day time road closure between 7.00am to 7.00pm.
The Drives, High Wycombe – Whole length of road : Tuesday 23rd April 2019 to Monday 29th April 2019 – Micro surfacing prep works taking place using a day time road closure between 7.00am to 7.00pm.
Carriageway surfacing – Plane and Patch programme
Mead Way, Oving – Various locations along length of road : Tuesday 23rd April 2019 – Plane and Patch works taking place using a day time road closure between 7.00am and 6.00pm.
Pulpit Lane, Oving – Various locations along length of road : Wednesday 24th April 2019 to Friday 26th April 2019 – Plane and Patch works taking place using a day time road closure between 7.00am and 6.00pm.
Easington Lane, Easington – Various locations along length of road : Tuesday 23rd April 2019 to Wednesday 24th April 2019 – Plane and Patch works taking place using a day time road closure between 7.00am and 6.00pm.
Winchendon Road, Chearsley – Various locations along length of road : Tuesday 23rd April 2019 to Tuesday 7th May 2019 – Plane and Patch works taking place using a day time road closure between 9.30am and 3.30pm.
Crendon Road, Shabbington – Various locations along length of road : Thursday 25th April 2019 to Friday 26th April 2019 – Plane and Patch works taking place using a day time road closure between 9.30am and 3.30pm.
St Marys Road, Wexham – Various locations along length of road : Tuesday 23rd April 2019 to Thursday 25th April 2019 – Plane and Patch works taking place using a day time road closure between 8.00am and 5.00pm.
Albion Road, Booker, High Wycombe – Various locations along length of road : Thursday 25th April 2019 to Saturday 27th April 2019 – Plane and Patch works taking place using localised traffic management between 8.00am and 5.00pm.
Oak Crescent, Cressex – Various locations along length of road : Tuesday 23rd April 2019 to Wednesday 24th April 2019 – Plane and Patch works taking place using a day time road closure between 7.00pm and 6.00am.
Huntercombe Lane South, Burnham – Various locations along length of road : Friday 26th April 2019 to Sunday 28th April 2019 – Plane and Patch works taking place using a day time road closure between 8.00am and 5.00pm.
Footway surfacing
High Street, Chesham – White Hill to The Broadway : Monday 8th April 2019 to Friday 26th April 2019 – Footway block paving and drainage works taking place using a footway and road closure between 8.00am and 6.00pm.