Roadworks for the week ahead – Mon 1st July 2019
Week commencing Monday 1st July 2019 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme and, as some activities are weather dependent, dates may change at short notice.
Carriageway surfacing
A413 Amersham Bypass, Amersham – Whole length : Monday 1st July 2019 to Wednesday 3rd July 2019 – Conventional surfacing works taking place using a night time road closure between 7.00pm to 6.00am.
Penmoor Close, Sands – Whole length : Monday 1st July 2019 – Surface dressing preparatory patching works taking place using a day time road closure between 7.00am to 7.00pm.
Main Road, Dinton – Portway to A418 : Monday 1st July 2019 to Monday 8th July 2019 – Surface dressing preparatory patching works taking place using a day time road closure between 7.00am to 7.00pm.
Swan Lane, The Lee – Chesham Lane to Jenkins Lane : Tuesday 2nd July 2019 to Wednesday 10 July 2019 – Surface dressing preparatory patching works taking place using a day time road closure between 7.00am to 7.00pm.
Langley Park Road, Iver – Cecil Road to Hollybush Lane : Thursday 4th July 2019 to Monday 15th July 2019 – Conventional surfacing works taking place using a night time road closure between 7pm to 6am each week night and a 24 hrs closure in place over the weekend of the 6th and 7th July 2019 to carry out resurfacing of the roundabout at the junction of Wood Lane.
Highland Road, Amersham – Stanley Hill Avenue to Hyrons Lane : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing preparatory patching works taking place using a day time road closure between 7.00am and 7.00pm.
Stanley Hill Avenue, Amersham – Stanley Hill to Hazel Park : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing preparatory patching works taking place using a day time road closure between 7.00am and 7.00pm.
Cressex Road, High Wycombe – A4010 to Marlow Road : Monday 1st July 2019 to Thursday 4th July 2019 – Micro-surfacing preparatory patching works taking place using a day time road closure between 7.00am and 7.00pm.
Dukes Wood Avenue, Gerrards Cross – Dukes Wood Avenue to A40 : Wednesday 3rd July 2019 to Friday 5th July 2019 – Micro-surfacing preparatory patching works taking place using a day time road closure between 7.00am and 7.00pm.
Frederick Street, Waddesdon – A41 to Quainton Road : Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Quarrendon Avenue, Aylesbury – Meadowcroft to Lay Road : Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Holland Road, Aylesbury – Quarrendon Avenue – Stonehaven Road : Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Masons Court, Aylesbury – Fowler Road to end : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Stephenson Close, Aylesbury – Fowler Road to end : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Rochester Place, Aylesbury – Fowler Road to end : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Sheriff Close, Aylesbury – Fowler Road to end : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
St Anthony’s Close, Aylesbury – Fowler Road to end : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
St Hilda’s Court, Aylesbury – Fowler Road to end : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
St Edmunds Close, Aylesbury – Fowler Road to end : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Chesterfield Place, Aylesbury – Fowler Road to end : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro Surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Keble Close, Aylesbury – Fowler Road to end : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
St Catherine’s Court, Aylesbury – St Anne’s Road to end : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
St Anne’s Road, Aylesbury – Fowler Road to end : Monday 1st July 2019 to Tuesday 2nd July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Meare Estate Roads, Wooburn Green – A4094 to A4094 : Monday 1st July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Heath Road, Beaconsfield – Holtspur Top Lane to end : Monday 1st July 2019 to Thursday 4th July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Wood Way, Beaconsfield – Heath Road to end : Monday 1st July 2019 to Thursday 4th July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
East Way, Beaconsfield – Heath Road to end : Monday 1st July 2019 to Thursday 4th July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
South Way, Beaconsfield – Heath Road to end : Monday 1st July 2019 to Thursday 4th July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Long View, Beaconsfield – Heath Road to end : Monday 1st July 2019 to Thursday 4th July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Buckingham Drive, High Wycombe – Micklefield Road to end : Thursday 4th July 2019 to Saturday 6th July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Buckingham Close, High Wycombe – Buckingham Drive to end : Thursday 4th July 2019 to Saturday 6th July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Farm Close, High Wycombe – Winslow Gardens to end : Thursday 4th July 2019 to Saturday 6th July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Tilling Crescent, High Wycombe – Buckingham Drive to Buckingham Drive : Thursday 4th July 2019 to Saturday 6th July 2019 – Micro-surfacing works taking place using a day time road closure between 8.00am and 5.00pm.
Main Street, Twyford – Portway Road to Church Street : Monday 1st July 2019 to Wednesday 3rd July 2019 – Ironwork adjustments taking place using local traffic management between 9.30am and 3.30pm.
Church Street, Twyford – Main Street to end : Monday 1st July 2019 to Wednesday 3rd July 2019 – Ironwork adjustments taking place using local traffic management between 9.30am and 3.30pm.
School Lane, Twyford – Main Street to end : Wednesday 3rd July 2019 to Thursday 4th July 2019 – Ironwork adjustments taking place using local traffic management between 9.30am and 3.30pm.
Portway Road, Twyford – Main Street to Gawcott Road : Friday 5th July 2019 to Saturday 6th July 2019 – Ironwork adjustments taking place using local traffic management between 9.30am and 3.30pm.
Highways structures maintenance
Chapel Road, Ford (near Aylesbury) – Bridge over the Meadle Brook : Monday 1st July 2019 to Friday 5th July 2019 – Bridge wing wall reconstruction using local traffic management between 7.30am and 6.00pm.
Chapel Lane, High Wycombe – Gallows Lane junction to Toweridge Lane junction : Monday 1st July 2019 to Friday 5th July 2019 – Major maintenance to concrete retaining wall using two way traffic signals between 9.30am and 3.30pm.
Drainage works
Flaunden Hill, Latimer – Outside Home Farm : Monday 24th June to Tuesday 9th July 2019 – Drainage improvement works using a daytime road closure between 8.00am and 5.00pm.
West Lane, Bledlow – Near to Bakehouse Farm : Monday 1st July 2019 to Wednesday 10th July 2019 – Drainage improvement works using a daytime road closure between 8.00am and 5.00pm.
Traffic signal refurbishment
Friarage Road, Aylesbury – Roundabout with Station Way to junction of Rickfords Hill : Monday 1st July 2019 to Friday 26th July 2019 – Traffic signal refurbishment works using daytime lane closures with closure of the existing crossing between 9.30am and 3.30pm. From Monday 8th July 2019 pedestrian access to Morrisons & the bus stop on the south side of Friarage Road will be closed for approximately 2 weeks.