Roadworks for the week ahead – Monday 25th May 2020
Week commencing Monday 25th May 2020 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Surfacing Schemes
A40 White Hill, Holtspur – Double roundabouts only at the junction with B4440 Wooburn Green Lane & Holtspur Top Lane : Tuesday 26th May 2020 to Sunday 31st May 2020 – Resurfacing works using temporary traffic lights on the A40 and road closures along Wooburn Green Road and Holtspur Top Lane 24 hours a day.
Welsh Lane, Biddlesden – Stowe Park junction to 30mph limit sign : Tuesday 26th May 2020 to Friday 19th June 2020 – Patching works using a daytime road closure between 7.00am and 7.00pm
Fieldhouse Lane, Marlow – Various locations along road : Tuesday 26th May 2020 – Patching works using a daytime road closure between 7.30am and 4.30pm.
Lock Road, Marlow – Various locations along road : Wednesday 27th May 2020 to Tuesday 2nd June 2020 – Patching works using a daytime road closure and temporary traffic lights between 7.30am and 4.30pm.
Drainage Programme
A404 Amersham Road, Hazelmere – Junction with Eastern Dene : Tuesday 26th May 2020 to Wednesday 27th May 2020 – Drainage improvements using temporary traffic lights between 9.00am and 4.00pm.
Orchard Road, Seer Green – Junction with School Lane : Tuesday 26th May 2020 to Friday 29th May 2020 – Drainage improvements using temporary traffic lights between 8.00am and 5.00pm.
Ballinger Road, The Lee – Oxford Street to Chartridge Lane : Tuesday 26th May 2020 to Friday 29th May 2020 – Drainage improvements using temporary traffic lights between 8.00am and 5.00pm.
Lower Road, Loosley Row – Outside Loosley House : Tuesday 26th May 2020 to Friday 29th May 2020 – Drainage improvements using temporary traffic lights between 8.00am and 5.00pm.
Bridge Improvements
High Street, Marlow – Marlow Bridge : Monday 25th May 2020 to Friday 10th July 2020 – Bridge refurbishment using a 24/7 road closure until Monday 1 June and then 24/7 two-way traffic lights between 8am and 6pm until Friday 10th July 2020.
*Source of article : Buckinghamshire Council.