Roadworks for the week ahead – Monday 26th October 2020

| October 26, 2020

Week commencing Monday 26th October 2020 Transport for Buckinghamshire will be carrying out work at the following locations.

The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.

Plane and Patch Programme

Welsh Lane, Biddlesden – Stowe Park Junction to 30 mph limit sign : Monday 26th October 2020 to Friday 6th November 2020 – Carriageway patching works using a daytime road closure in operation between 7.00am and 7.00pm.

Micro Surfacing Programme

Lansdowne Road, Chesham – Various locations : Monday 26 October 2020 to Tuesday 27th October 2020 – Carriageway Iron Works using a daytime road closure in operation between 7.00am and 7.00pm.

Quarrendon Road and side roads, Amersham – Various locations : Tuesday 27th October 2020 to Monday 3rd November 2020 – Carriageway Iron Works using a daytime road closure in operation between 7.00am and 7.00pm.

Joint sealing Programme

Dadford Road, Silverstone – Club Corner Roundabout : Monday 26th October 2020 – Carriageway Joint Sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Dadford Road, Silverstone – Roundabout at car park entrance : Tuesday 27th October 2020 – Carriageway Joint Sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Stratford Road, Thornborough – Foscote turn to Thornton turn : Wednesday 28th October 2020 to Thursday 29th October 2020 – Carriageway Joint Sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Oxford Road, Stone – Roundabout at junction with Coldharbour Way : Friday 30th October 2020 – Carriageway Joint Sealing works using a night time road closure in operation between 7.00pm and 6.00am.

Bridge Improvement Programme

Ivy Lane, Great Brickhill – Bridge adjacent to the Three Locks Golf Club to Heath Road : Monday 26th October 2020 to Friday 30th October 2020 – Emergency Bridge Repairs using a road closure in operation 24 / 7.

B488 Horton Road, Ivinghoe – 200m either side of the Grand Union Canal bridge : Monday 26th October 2020 to Friday 20th November 2020 – Bridge Strengthening repairs using a 24 hour closure.

High Street / West Street / Spittal Street, Marlow – Marlow Obelisk : Tuesday 27th October 2020 to Thursday 29th October 2020 – Obelisk Repairs using temporary traffic signals in operation between 9.00pm and 6.00am.

Footway Structural Repair Programme

Cottesloe Road, Aylesbury – Churchill Avenue to Clover Lane : Monday 26th October 2020 to Friday 27th November 2020 – Footway Improvement works using localised traffic management in operation between 7.30am and 4.30pm.

London Road, Great Missenden – School playing field entrance to fire station : Monday 26th October 2020 to Friday 20th November 2020 – Footway Improvement works using temporary traffic signals in operation between 9.30am and 3.30pm (3.00pm during school term time)

Drainage Improvement Schemes

South Road, Chesham Bois – Junction with Sycamore Road : Monday 26th October 2020 to Tuesday 27th October 2020 – Drainage Improvement Works using temporary traffic signals in operation between 8.00am and 5.00pm.

Jordans Lane, Seer Green – Outside Longlands : Thursday 29th October 2020 to Monday 10th November 2020 – Drainage Improvement Works using temporary traffic signals in operation between 8.00am and 5.00pm.

Grovers Court, Princes Risborough – in cul-de-sac : Wednesday 28th October 2020 to Monday 3rd November 2020 – Drainage Improvement Works using localised traffic management in operation between 8.00am and 5.00pm.

Missenden Road / Wey Lane / Church Street, Chesham : Monday 26th October 2020 to Wednesday 23rd December 2020 – Installation of new culvert using a road closure in operation 24 / 7.

Covid – Active Travel Plan

Southcourt, Aylesbury – Various locations : Wednesday 28th October 2020 to Tuesday 10th November 2020 – Pop up cycleway / Planters for point closures / lining works and additional signage using mobile works and temporary traffic signals in operation between 8.00am and 4.00pm.

A40 London Road corridor improvements project

London Road, High Wycombe – Micklefield Junction : Friday 30th October 2020 – Civil works / gully maintenance / lining works for Signal crossing upgrade using localised traffic management and lane closures : eastbound and westbound maintaining one lane open at all times – between 9.30am and 3.30pm.

*Source of article : Buckinghamshire Council.