Roadworks for the week ahead – Monday 15th February 2021
Week commencing Monday 15th February 2021 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Conventional Resurfacing Programme
The Green, Bell Close, Lodge Lane, Stoke Hammond – Whole lengths of roads : Monday 15th February 2021 to Tuesday 16th February 2021 – Carriageway patching works using a daytime road closure in operation between 8.00am and 5.00pm.
Surface Dressing Programme
Leighton Road, Edlesborough – B489 to County Boundary : Wednesday 17th February 2021 to Thursday 24th February 2021 – Preparatory patching works using a daytime road closure in operation between 9.00am and 4.00pm.
City Road, Radnage – Town End Road to A40 : Monday 15th February 2021 to Thursday 25th February 2021 – Preparatory patching works using a daytime road closure in operation between 9.30am and 3.30pm.
Spurgrove Lane, Frieth – Frieth Hill to Innings Road : Monday 15th February 2021 to Tuesday 16th February 2021 – Preparatory patching works using a daytime road closure in operation between 7.30am and 4.30pm.
Welders Lane, Jordans – Jordans Lane to Grove Lane : Wednesday 17th February 2021 to Thursday 24th February 2021 – Preparatory patching works using a daytime road closure in operation between 7.30am and 4.30pm.
Footway Structural Repair Programme
New Road, Stokenchurch – Whole length of footway : Monday 15th February 2021 to Tuesday 23rd February 2021 – Footway Improvement works using localised traffic management in operation between 7.30am and 5.30pm.
Somerville Way, Aylesbury – Whole length of footway : Monday 15th February 2021 to Wednesday 17th February 2021 – Footway Improvement works using a footpath closure in operation between 7.30am and 5.30pm.
Wendover Road, Aylesbury – Cambourne Avenue to Eascote Road : Monday 15th February 2021 to Friday 5th March 2021 – Footway Reconstruction works using a footpath closure and lane controls in operation between 7.30am and 5.30pm.
Desborough Avenue, High Wycombe – Length of footways : Wednesday 17th February 2021 to Tuesday 23rd March 2021 – Footway reconstruction works using footway closures and temporary traffic signals in operation between 7.30am and 5.30pm.
Drainage Improvement Schemes
Meadowbank Close, Long Crendon – Various locations along close : Monday 15th February 2021 to Saturday 27th February 2021 – Drainage Improvement works using localised traffic management and temporary traffic signals in operation between 8.00am to 5.00pm.
*Source of article : Buckinghamshire Council.