Week commencing Monday 19th April 2021 Transport for Buckinghamshire will be carrying out work at the following locations.

The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.

Conventional Surfacing Programme

Ledborough Lane, Beaconsfield – B474 Penn Road to A355 Amersham Road : Monday 19th April 2021 to Monday 31st May 2021 – Carriageway reconstruction works using a road closure in operation 24 / 7.

Ardenham Street and Mount Pleasant, Aylesbury – various locations : Tuesday 20th April 2021 to Wednesday 21st April 2021 – Carriageway surfacing works using a road closure in operation between 7.30am and 6.00pm.

Surface Dressing Programme

Hogshaw – St John’s Lane to Carters Lane : Monday 19th April 2021 to Monday 26th April 2021 – Stabilisation and preparatory patching works using a road closure in operation 24 / 7.

Buckingham Road, Westbury – Westbury to Stowe / Water Stratford crossroads : Monday 19th April 2021 to Wednesday 28th April 2021 – Preparatory patching works using a daytime road closure in operation between 9.30am and 3.30pm.

Winslow Road, East Claydon – Sandhill Road, East Claydon to Granborough Road, Winslow : Monday 19th April 2021 – Preparatory patching works using a daytime road closure in operation between 7.30am and 6.00pm.

Footway Structural Repair Programme

Desborough Avenue, High Wycombe – Deeds Grove to Kitchener Road : Monday 19th April 2021 to Friday 23rd April 2021 – Footway reconstruction works using footway closures and temporary traffic signals in operation between 9.30am and 4.00pm.

Poles Hill, Chesham – Darvell Drive to Chapmans Crescent : Monday 19th April 2021 to Friday 30th April 2021 – Footway reconstruction works using localised traffic management in operation between 7.30am and 5.00pm.

Poppy Road, Princes Risborough – A4010 Wycombe Road to B4444 Station Road : Monday 19th April 2021 to Friday 30th April 2021 – Footway reconstruction works using footway closures and temporary traffic signals in operation between 7.30am and 5.00pm.

*Source of information : Buckinghamshire Council.