Roadworks for the week ahead – Monday 12th July 2021
Week commencing Monday 12th July 2021 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Conventional Resurfacing Programme
A418, Aylesbury Road, Bierton – North of Bierton to Wing : Monday 12th July 2021 to Friday 16th July 2021 – Coring works using temporary traffic signals and stop and go traffic management in operation between 9.30am and 3.30pm.
Micro Surfacing Programme
Townsend Cottages, Great Horwood – Various locations along length of road : Monday 12th July 2021 – Micro surfacing preparatory patching works using localised traffic management in operation between 7.30am and 4.30pm.
Willow Road, Great Horwood – Various locations along length of road : Monday 12th July 2021 – Micro surfacing preparatory patching works using localised traffic management in operation between 7.30am and 4.30pm.
Spring Lane, Great Horwood – Various locations along length of road : Tuesday 13th July 2021 to Thursday 15th July 2021 – Micro surfacing preparatory patching works using localised traffic management in operation between 7.30am and 4.30pm.
Sedgemoor Road, Flackwell Heath – Various locations along length of road : Friday 16th July 2021 to Monday 19th July 2021 – Micro surfacing preparatory patching works using a road closure in operation between 7.30am and 4.30pm.
Rowan Avenue, High Wycombe – Various locations along length of road : Monday 12th July 2021 to Friday 16th July 2021 – Micro surfacing preparatory patching works using localised traffic management in operation between 7.30am and 4.30pm.
Harriers Way / Fox Road, Holmer Green – Various locations along length of road : Monday 12th July 2021 to Wednesday 14th July 2021 – Micro surfacing preparatory patching works using localised traffic management in operation between 7.30am and 4.30pm.
Mayflower Way Estate Roads – Various locations along length of road : Wednesday 14th July 2021 to Friday 16th July 2021 – Micro surfacing preparatory patching works using localised traffic management in operation between 7.30am and 4.30pm.
Surface Dressing Programme
Wood Lane, Iver Heath – 5 points roundabout and Langley Park Road : Thursday 15th July 2021 – Surface Dressing works using a road closure in operation between 7.00am and 7.00pm.
Huntercombe Lane South, Lent Rise – A4 Bath Road to Lake End Road : Friday 16th July 2021 – Surface Dressing works using a road closure in operation between 7.00am and 7.00pm.
A4094 Ferry Lane, Wooburn – Hedsor Road to County Boundary : Friday 16th July 2021 – Surface Dressing works using a road closure in operation between 7.00am and 7.00pm.
City Road, Radnage – A4155 to Church Lane : Friday 16th July 2021 to Saturday 17th July 2021 – Surface Dressing works using a road closure in operation between 7.00am and 7.00pm.
Hammersley Lane, Tylers Green – Church Road to Chiltern Yard : Saturday 17th July 2021 to Sunday 18th July 2021 – Surface Dressing works using a road closure in operation between 7.00am and 7.00pm.
Welders Lane – Jordans Lane to Grove Lane : Sunday 18th July 2021 – Surface Dressing works using a road closure in operation between 7.00am and 7.00pm.
Gorelands Lane, Chalfont St Giles – Shire Lane to B442 Nightingales Lane : Sunday 18th July 2021 to Monday 19th July 2021 – Surface Dressing works using a road closure in operation between 7.00am and 7.00pm.
Drainage Improvement Programme
Green Common Lane, Beaconsfield – Royal Charter Pub down to T Raynor and Son : Monday 12th July 2021 until Friday 16th July 2021 – Drainage Improvement works using a road closure in operation 24 / 7.
School Lane, Seer Green – Various locations along length of road : Monday 12th July 2021 to Friday 23rd July 2021 – Drainage Improvement works using temporary traffic signals in operation between 9.30am and 3.30pm.
Junction Improvement Works
Crest Road, High Wycombe Signalisation : Continuation of major works to convert the existing roundabout on A4010 John Hall Way into a signalised junction with Crest Road, with completion anticipated early September 2021.
A41 Bicester Road, Aylesbury – Rabans Lane to Paradise Orchard : Installation of ducting across the A41 carriageway in 2 locations, installation of CCTV cameras, communications cabinets.
Local Improvement Schemes
Great Missenden C of E School, Church Street, Great Missenden – Car Park and Turning Head : Monday 12th July 2021 – Friday 6th August 2021 – Surfacing and lining works, not on highway but with localised traffic management, in operation between 7.30am and 4.30pm.
Structures Improvement Programme
Cattleford Bridge, A422 Stratford, Nr Buckingham – Cattleford Bridge : Monday 12th July 2021 to Friday 27th August 2021 – Bridge Refurbishment using temporary traffic signals in operation 24 / 7.
High Street, Marlow – Marlow Suspension Bridge : Monday 12th July 2021 to Friday 16th July 2021 – Bridge Inspection and survey works using two-way traffic signals and localised traffic management in operation between 9.30am to 3.30pm and 8.00pm to 6.00am.
*Source of information : Buckinghamshire Council.