Web Analytics

Roadworks in Buckinghamshire for the week ahead – Monday 15th November 2021

| November 13, 2021

Week commencing Monday 15th November 2021 Transport for Buckinghamshire will be carrying out work at the following locations.

The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.

Conventional Surfacing Programme

A404 Amersham Hill, High Wycombe : Thursday 4th November 2021 to Tuesday 16th November 2021 – Surfacing works using a night time road closure in operation Monday to Friday between 8.00pm and 6.00am.

A4007 Slough Road, Iver : Wednesday 17th November 2021 to Sunday 21st November 2021 – Surfacing works using a road closure in operation Monday to Friday between 8.00pm and 6.00am and 24 / 7 closure at the weekend.

Plane and Patch Programme

Cogdells Lane, Chesham : Monday 15th November 2021 to Wednesday 17th November 2021 – Surface patching works using a road closure in operation Monday to Friday between 7.30am and 5.00pm.

Mill Lane, Chalfont St Giles : Thursday 18th November 2021 – Surface patching works using a road closure in operation Monday to Friday between 7.30am and 5.00pm.

Lancaster Road, High Wycombe : Thursday 18th November 2021 to Friday 19th November 2021 – Surface patching works using a night time road closure in operation Monday to Friday between 8.00pm and 6.00am.

Colne Road, Iver : Friday 19th November 2021 to Tuesday 23rd November 2021 – Surface patching works using a road closure in operation Monday to Friday between 7.30am and 5.00pm.

Footway Improvement Works – Preparation works

Grove Road, Amersham – Roundwood Road to Quill Hall Lane : Wednesday 10th November 2021 to Wednesday 17th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.

Dunstable Road, Ivinghoe : Monday 15th November 2021 to Friday 19th November 2021 – Footway improvement works using a footway closure and three way lights in operation Monday to Friday between 8.00am and 4.00pm.

Marsham Way, Gerrards Cross – Mill Lane to Packhorse Road : Wednesday 17th November 2021 to Friday 26th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.

Footway Improvement Works – Headline treatment works

Harries Way, Holmer Green : Tuesday 9th November 2021 to Monday 15th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.

Battings Wood Gardens, Naphill : Friday 12th November 2021 to Thursday 18th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.

Ambleside, Aylesbury : Monday 15th November 2021 to 23rd December 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 6.00pm.

Freemantle Road, Aylesbury : Monday 15th November 2021 to 14th December 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 6.00pm.

Hulbert End, Aylesbury : Tuesday 16th November 2021 to Friday 19th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.

Harvey Road, Aylesbury – Mandeville Road to Barnard Crescent : Thursday 18th November 2021 to Friday 26th November 2021 – Footway improvement works using a footway closure and give and take in turn traffic management in operation Monday to Friday between 8.00am and 4.00pm.

Junction Improvement Works

A41 Bicester Road – Rabans Lane to Paradise Orchard including Jackson Road and Dickens Way, Aylesbury : Monday 20th September 2021 to June 2022 – Works will continue near to the Bicester Road junction with Sir Henry Lee Crescent / Paradise Orchard, on the North-West bound traffic lane 1. Works will involve excavation of the adjacent verge for the widening of the carriageway to create a new lane. Our works will include excavation for the installation of new kerbs, drainage and utility works, with a contraflow system setup to maintain 2-way traffic at all times. The working hours are Monday to Friday between 8.00am and 4.00pm.

Road Markings – Lining Refresh Scheme

A41 – Waddesdon to Bedgrove : Tuesday 26th October 2021 to Friday 19th November 2021 – Lining refreshment works using 2 / 3 and 4-way lights and lane closures in operation Monday to Friday between 9.00pm and 5.00am.

Bridge Schemes

High Street, Marlow – Marlow Bridge : Monday 4th October 2021 to Friday 4th February 2022 – Major bridge refurbishment using a footway closure when appropriate in operation Monday to Friday between 8.00am and 5.00pm.

Mill Lane, Taplow – Mill Lane Bridge : Monday 1st November 2021 to Friday 3rd December 2021 – Bridge demolition for Berry Hill Bridge; localised traffic management for site access point and compound area and a segregated area for pedestrians and cyclist movements. Monday to Friday between 8.00am and 4.00pm.

*Source of information : Buckinghamshire Council.

Comments are closed.