Roadworks in Buckinghamshire for the week ahead – Monday 26th September 2022
Week commencing Monday 26th September 2022 roadworks are scheduled to take place at the following locations in Buckinghamshire.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Microsurfacing Preparatory Works
St Francis Road, Denham – From Green Tiles Lane to Penn Drive : Monday 26th September 2022 – Microsurfacing preparatory patching works using a road closure in operation Monday to Friday between 7.00am to 7.00pm.
Park Lane, Hazlemere – From A404 Amersham Road Junction to Holmer Green Road : Monday 26th September 2022 – Microsurfacing preparatory patching works using a road closure in operation Monday to Friday between 7.00am to 7.00pm.
Clearbrook Close, High Wycombe : Tuesday 27th September 2022 – Microsurfacing preparatory patching works using a road closure in operation Monday to Friday between 7.00am to 7.00pm.
Kendalls Close, High Wycombe : Tuesday 27th September 2022 – Microsurfacing preparatory patching works using a road closure in operation Monday to Friday between 7.30am to 7.30pm.
Back Lane, Chalfont St Giles : Wednesday 28th September 2022 to Thursday 29th September 2022 – Microsurfacing preparatory patching works using a road closure in operation Monday to Friday between 7.00am to 7.00pm.
Abbotswood, Speen : Wednesday 28th September 2022 to Thursday 29th September 2022 – Microsurfacing preparatory patching works using a road closure in operation Monday to Friday between 7.00am to 7.00pm.
Lansdowne Way, High Wycombe : Wednesday 28th September 2022 to Tuesday 4th October 2022 – Microsurfacing preparatory patching works using a road closure in operation Monday to Friday between 7.30am to 7.30pm.
Fleetwood Close, Chalfont St Giles : Friday 30th September 2022 – Microsurfacing preparatory patching works using a road closure in operation Monday to Friday between 7.30am to 7.30pm.
Microsurfacing Headline Works
Roberts Road, High Wycombe : Monday 26th September 2022 – Microsurfacing headline treatment works using a road closure in operation Monday to Friday between 7.00am to 7.00pm.
Sedgmoor Road, Flackwell Heath : Tuesday 27th September 2022 to Wednesday 28th September 2022 – Microsurfacing headline treatment works using a road closure in operation Monday to Friday between 7.00am to 7.00pm.
Lye Green Road, Chesham – From Botley Road to Lycrome Road : Wednesday 28th September 2022 to Thursday 29th September 2022 – Microsurfacing headline treatment works using a road closure in operation Monday to Friday between 7.00am to 7.00pm.
Fieldhouse Lane, Marlow : Friday 30 September 2022 – Microsurfacing headline treatment works using a road closure in operation Monday to Friday between 7.00am to 7.00pm.
Hughenden Road, High Wycombe : Saturday 1st October 2022 to Sunday 2nd October 2022 – Microsurfacing headline treatment works using a road closure in operation Saturday and Sunday between 7.00am to 7.00pm.
Safety Barrier Works
A41 Bicester Road, Grendon Underwood – At the junction with The Broadway : Monday 26th September 2022 to Friday 30th September 2022 – Safety barrier investigation works using three-way temporary traffic lights in operation Monday to Friday between 9.30am and 3.30pm.
A41 Aston Clinton Bypass, Aston Clinton – From Woodlands Roundabout to Tring Hill Slip Roads : Safety barrier terminal upgrade works using lane closures and slip road closures in operation Monday to Friday between 9.30am and 3.30pm.
Bridge Schemes
High Street, Marlow – Marlow Bridge : Tuesday 5th October 2022 2021 to Friday 25th November 2022 – Major bridge refurbishment using a footway closure when appropriate in operation Monday to Friday between 8.00am and 5.00pm.
Highway Infrastructure Projects (HIPs)
A41 Bicester Road – Rabans Lane to Paradise Orchard including Jackson Road and Dickens Way, Aylesbury : From Monday 12th September 2022 to 14th October 2022 work will continue on the realignment of the ditch from the Pegasus crossing to Paradise Orchard traffic signals, the westbound inside lane will be closed off to traffic 24 / 7. For five days from Monday 26th September 2022 several street light columns and lanterns will be replaced at the new Jackson Road traffic signal junction, this will be carried out using lane closures.
*Source of information : Buckinghamshire Council.