Roadworks in Buckinghamshire for the week ahead – Monday 6th February 2023
Week commencing Monday 6th February 2023 roadworks are scheduled to take place at the following locations in Buckinghamshire.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Conventional Surfacing Works
Risborough Road, Aston Sandford : Monday 16th January 2023 to Tuesday 7th February 2023 – Resurfacing works using recycled material using a road closure in operation Monday to Friday between 7.30am and 4.00pm.
Footway Improvement Works
Broughton Avenue, Aylesbury – From Richmond Road to Parton Road : Monday 17th October 2022 to Friday 10th February 2023 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Picts Lane, Princes Risborough – From Station Road to Shootacre Lane : Monday 30th January 2023 to Friday 3rd March 2023 – Footway and carriageway improvement works using a footway closure and multi-way lights in operation Monday to Friday between 8.00am and 6.00pm.
Station Road, Marlow – From High Street to St Peter Street : Monday 6th February 2023 to Friday 10th February 2023 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Community Board Works
High Street, Burnham – Outside No. 27 and No. 4b : Monday 6th February 2023 to Thursday 9th February 2023 – Installing pedestrian dropped kerb and tactile paving using multi-way lights, give and take and a footway closure in operation Monday to Friday between 9.30am to 3.30pm.
Network Safety / Improvement Works
Woodside Road / Chiltern Avenue, Amersham : Monday 23rd January 2023 to Thursday 9th February 2023 – Upgrading pedestrian crossing point, installing new signage and lining works using three-way temporary traffic lights in operation Monday to Friday between 9.30am and 3.30pm.
Oxford Road, Denham – Outside of Burger Kebab Galaxy : Monday 6th February 2023 to Friday 3rd March 2023 – Pedestrian crossing upgrade and bollard installation using three-way lights in operation Monday to Friday between 9.30am and 3.30pm in the school term time and 8.00am and 6.00pm during school half term.
Safety Barrier Repair Works
A41 Bicester Road, Grendon Underwood – With the junction of The Broadway : Monday 23rd January 2023 to Friday 24th February 2023 – Safety barrier repair works using three-way temporary traffic lights in operation Monday to Friday between 9.30am and 3.30pm.
Highway Infrastructure Projects (HIPs)
A41 Bicester Road – Rabans Lane to Paradise Orchard including Jackson Road and Dickens Way, Aylesbury : From Monday 9th January 2023 until Friday 3rd March 2023, we will be carrying out drainage works, replacing traffic signs and defect repairs, using lane incursions in operation Monday to Friday between 8.00am and 4.00pm.
*Source of information : Press release from Buckinghamshire Council.