Week commencing Monday 6th November 2023 roadworks are scheduled to take place at the following locations in Buckinghamshire.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Conventional Surfacing Works
A41 Bicester Road Woodham : Monday 6th November 2023 to Saturday 14th November 2023 – Conventional surfacing works using a full road closure between 8.00pm to 6.00am.
Farnham Road, Farnham Royal : Tuesday 7th November 2023 to Friday 10th November 2023 – Conventional surfacing works using a full road closure between 8.00pm to 6.00am. Phase 1 – Tockley Road and Bredwood Close : Monday 6th to Friday 10th November 2023 – Conventional surfacing works using a full road closure between 7.00am to 7.00pm.
Footways Resurfacing Works
Wellesley Avenue, Iver – Richings Way to Bathurst Walk : Monday 2nd October 2023 to Saturday 18th November 2023 – Footway resurfacing works using a footway closure and multi way traffic signals between 8.00am to 5.00pm.
Amersham Road, Chesham Bois – Speed Limit Sign (near Chiltern Road entrance) to The Leys : Monday 30th October 2023 to Friday 1st December 2023 – Footway resurfacing works using a footway closure between 10.00am and 3.00pm.
Drainage Works
Kingsmead, Monks Risborough : Monday 30th October 2023 to Friday 15th December 2023 – Drainage works using both a road closure and give and take traffic management between 8.00am and 5.00pm.
Network Improvement Works
A422 Brackley Road, Westbury – From 50m West of Playing Fields Road to 50m East of Main Street : Monday 23rd October 2023 to Friday 10th November 2023 – Installation of a puffin crossing. Works will be carried out under 4-way lights, 9.30am to 3.30pm.
Highway Traffic Signals
B4443 Black Bridge, Stoke Road / Mandeville Road, Aylesbury : Monday 23rd October 2023 to Friday 10th November 2023 – Upgrade of the traffic signals using multi-way traffic signals.
Street Lighting – Various locations in Marlow : Monday 23rd October 2023 to Friday 10th November 2023 – As part of a rolling program of works, street lighting will be replacing various obsolete lanterns across Buckinghamshire starting in Marlow converting 427 lanterns. These will all be upgraded with LED energy efficient lighting achieving approximately 70% energy saving, whilst providing better quality lighting and leading to reduced future maintenance costs.
Road Lining Works
A40 West Wycombe Road / Oxford Road, High Wycombe : Monday 6th November 2023 to Saturday 11th November 2023 – Road lining refreshing works using multi-way traffic lights between 9.00pm to 5.00am over five nights.
Beaconsfield Interchange, Beaconsfield : Monday 6th November 2023 to Saturday 18th November 2023 – Road lining refreshing works using a lane closure between 9.00pm and 5.00am.
*Source of information : Press release from Buckinghamshire Council.