Road surfacing works week commencing 22nd May 2017

| May 21, 2017

Road repairs: A pothole crew in action.

Week commencing Monday 22nd May 2017 Transport for Buckinghamshire will be carrying out work at the following locations.

The dates shown are subject to change at short notice.

No weekend working is planned this week.

Footway Surfacing Schemes

High Street/Market Square, Chesham : Monday 22nd May 2017 to Friday 26th May 2017 – Daytime upgrade of the existing block paving along the eastern footway along with the repair of localised drainage issues, the replacement of the existing drainage channel and targeted tree maintenance work using localised footway closures and carriageway restrictions between 8.00am and 6.00pm.

Market Square, Aylesbury : Monday 22nd May 2017 to Friday 26th May 2017 – Daytime and night time targeted maintenance work to existing block paving in the carriageway and footways along with the repair of localised drainage issues and the removal of the rising bollard assembly, using localised footway closures and carriageway restrictions. Work within the carriageway will be restricted to night time working only using road closures between 6.00pm and 6.00am. Daytime working on market days will be restricted to localised footway closures between 10.00am and 4.00pm.

Road Surfacing Schemes

Abercromby Avenue, High Wycombe – Oakridge Road to Desborough Park Road : Monday 22nd May 2017 – Friday 26th May 2017 – Daytime preparation works for Micro-surfacing programme using a road closure between 7.00am and 7.00pm.

A416 Broad Street & Berkhamsted Road, Chesham – White Hill to Britannia Road : Monday 22nd May 2017 to Tuesday 30th May 2017 – Daytime ironwork adjustments using three way signals between 9.30am and 3.30pm.

Chilton Road, Long Crendon : Monday 22nd May 2017 – Daytime ironwork adjustments using three way traffic signals between 7.00am and 7.00pm.

Orchard Way, Long Crendon : Monday 22nd May 2017 – Daytime ironwork adjustments using three way traffic signals between 7.00am and 7.00pm.

Chesham Lane/Denham Lane, Chalfont St Peter : Tuesday 23rd May 2017 – Wednesday 24th May 2017 – Daytime ironwork adjustments using three way traffic signals between 7.00am and 7.00pm.

Gold Hill West, Chalfont St Peter : Tuesday 23rd May 2017 – Wednesday 24th May 2017 – Daytime ironwork adjustments using three way traffic signals between 7.00am and 7.00pm.

Grove Lane, Chalfont St Peter : Tuesday 23rd May 2017 – Wednesday 24th May 2017 – Daytime ironwork adjustments using three way traffic signals between 7.00am and 7.00pm.

Wexham Street, Wexham : Thursday 25th May 2017 – Daytime ironwork adjustments using three way traffic signals between 7.00am and 7.00pm.