Roadworks for the week ahead – Mon 10th June 2019
Week commencing Monday 10th June 2019 Transport for Buckinghamshire will be carrying out work at the following locations.
The works are part of a rolling programme and, as some activities are weather dependent, dates may change at short notice.
Carriageway Surfacing Schemes – Conventional Surfacing Programme
Buckingham Ring Road, Buckingham – Gawcott Roundabout to Tingewick Road Roundabout : Tuesday 11th June 2019 to Friday 21st June 2019 – Conventional surfacing works taking place using a night time road closure between 7.00pm to 6.00am including the weekend of the 15th and 16th June 2019 with three-way traffic signals in operation from 6.00am until 7.00pm on the 15th and 16th June 2019.
Carriageway Surfacing Schemes – Surface Dressing Programme
A413 Buckingham Road, Whitchurch – Oving Road to Dunton Road : Monday 10th June 2019 – Surface Dressing preparatory patching works taking place using a night time road closure between 7.00pm to 6.00am.
Nightingales Lane, Little Chalfont – A413 to Cokes Lane : Friday 7th June 2019 to Thursday 20th June 2019 – Surface Dressing preparatory patching works taking place using a day time road closure between 9.30am to 3.30pm.
Chestnut Avenue, Halton – Village to B4009 : Monday 10th June 2019 to Tuesday 11th June 2019 – Surface Dressing preparatory patching works taking place using a day time road closure between 8.00am to 4.00pm.
High Street, Cheddington – Tennis Courts to B489 : Tuesday 11th June 2019 to Friday 21st June 2019 – Surface Dressing preparatory patching works taking place using a day time road closure between 7.00am to 7.00pm.
Radclive Road, Gawcott – Gawcott to Gawcott village : Wednesday 12th June 2019 to Monday 17th June 2019 – Surface Dressing preparatory patching works taking place using a day time road closure between 8.00am to 4.00pm.
Carriageway Surfacing Schemes – Micro-surfacing Programme
Langley Park Road, Iver – Mansion Lane to Cecil Road : Monday 10th June 2019 – Jetting works taking place using stop/go boards between 9.30am and 3.30pm.
Bourton Road, Buckingham – A413 Buckingham Ring Road East to Fire Station : Monday 10th June 2019 to Tuesday 11th June 2019 – Micro-surfacing works taking place using a day time road closure between 9.30am to 4.00pm.
Narcot Lane, Chalfont St Giles – Three Households Lane to Woodlands Farm : Tuesday 11th June 2019 to Wednesday 12th June 2019 – Jetting works taking place using stop/go boards between 9.30am and 3.30pm.
Main Street, Twyford – Portway Road to School Lane : Wednesday 12th June 2019 to Thursday 13th June 2019 – Micro-surfacing works taking place using a day time road closure between 9.30am to 3.00pm.
School Lane, Twyford – Main Street to End : Wednesday 12th June 2019 to Thursday 13th June 2019 – Micro-surfacing works taking place using a day time road closure between 9.30am to 4.00pm.
Church Street, Twyford – Main Street to End : Wednesday 12th June 2019 to Thursday 13th June 2019 – Micro-surfacing works taking place using a day time road closure between 9.30am to 4.00pm.
Coates Lane, Downley – Littleworth Road to Manor Gardens : Wednesday 12th June 2019 to Tuesday 18th June 2019 – Micro-surfacing preparatory works taking place using a day time road closure between 7.30am to 7.00pm.
Portway Road, Twyford – Main Street to Gawcott Road : Thursday 13th June 2019 to Monday 17th June 2019 – Micro-surfacing works taking place using a day time road closure between 9.30am to 4.00pm.
Carriageway Surfacing Schemes – Plane and Patch Programme
Watery Lane, Beachampton – Whole length : Monday 10th June 2019 – Plane and Patch works taking place using a day time road closure between 8.00am and 3.30pm.
Structures Programme
Chapel Lane, High Wycombe – Gallows Lane Junction – Toweridge Lane Junction : Monday 20th May 2019 to Friday 28th June 2019 – Major maintenance to concrete retaining wall using two way traffic signals between 9.30am and 3.30pm.