Roadworks in Buckinghamshire for the week ahead – Monday 28th November 2022
Week commencing Monday 28th November 2022 roadworks are scheduled to take place at the following locations in Buckinghamshire.
The works are part of a rolling programme. As some activities are weather dependent the dates may change at short notice.
Conventional Resurfacing Works
The Common, Stokenchurch : Monday 21st November 2022 to Tuesday 29th November 2022 – Resurfacing works using a road closure in operation Monday to Friday between 7.30am and 5.00pm.
Black Park Road, Wexham – From A412 Uxbridge Road to Rowley Lane : Monday 21st November 2022 to Wednesday 30th November 2022 – Resurfacing works on the A412 Uxbridge Road junction with Black Park Road using a road closure on Black Park Road and lane closures on A412 Uxbridge Road : including a right-hand turn ban -, in operation 24 hours : including weekend working -. We will also be carrying out gully emptying and ditching works near the junction of Rowley Lane with Black Park Road using give and take traffic management in operation Monday to Sunday between 8.00am to 5.00pm.
Oxford Road, High Wycombe – From Arch Way Roundabout to Bellfield Road : Monday 28th November 2022 to Friday 2nd December 2022 – Lining works after recent resurfacing works using a road closure in operation Monday to Saturday between 8.00pm and 6.00am.
Hithercroft Road, High Wycombe : Wednesday 30 November 2022 to Thursday 1st December 2022 – Resurfacing works using a road closure in operation Monday to Friday between 7.30am and 5.00pm.
‘Failed Road’ Schemes
North Lee Lane, Aylesbury : Monday 28th November 2022 to Wednesday 7th December 2022 – Road resurfacing using recycled material using a road a road closure in operation Monday to Sunday between 7.00am to 7.00pm with the closure remaining in place overnight and at the weekend to prevent through traffic damaging the unfinished surface. Temporary traffic lights will also be in place at the junctions of A4010 Risborough Road and Marsh Lane from Friday 2nd December 2022 to Wednesday 7th December 2022.
Microsurfacing Ironworks
Mill Road, Marlow : Thursday 24th November 2022 to Wednesday 30th November 2022 – Raising ironworks using a road closure and give and take traffic management in operation Monday to Saturday between 9.30am and 3.30pm.
Footway Improvement Works
Broughton Avenue, Aylesbury – From Richmond Road to Parton Road : Monday 17th October 2022 to Thursday 22nd December 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Dunsham Lane, Aylesbury – Ensbury Path to Lansdowne Road and No. 2 to No. 24 : Tuesday 15th November 2022 to Tuesday 29th November 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 9.30am and 3.30pm.
Hutchings Road, Beaconsfield : Monday 28th November 2022 to Friday 23rd December 2022 – Footway improvement works using a footway closure, three-way temporary traffic lights and give and take traffic management in operation Monday to Friday between 8.00am and 5.00pm.
Vicarage Lane, Steeple Claydon : Wednesday 30th November 2022 to Thursday 22nd December 2022 – Footway improvement works using a footway closure and give and take traffic management in operation Monday to Friday between 7.00am and 7.00pm.
Drainage Improvement Works
Fieldhouse Lane, Marlow – Approximately 100m south of the junction with Dedmere Lane : Monday 28th November 2022 to Friday 9th December 2022 – Drainage improvement works using 24-hour two-way temporary traffic lights.
Network Safety Improvement Works
A418 Aylesbury Road, Haddenham : Monday 28th November 2022 to Tuesday 6th December 2022 – Lining, road studs and sign installation works using a road closure in operation Monday to Saturday between 10.00pm and 5.00am.
Safety Barrier Works
A41 Aston Clinton Bypass, Aston Clinton – From Woodlands Roundabout to Tring Hill Slip Roads : Monday 14th November 2022 to Friday 2nd December 2022 – Safety barrier terminal upgrades and repairs using lane closures and slip road closures in operation Monday to Friday between 9.30am and 3.30pm.
Community Board Works
A41 Roman Road, Kingswood : Monday 28th November 2022 to Tuesday 29th November 2022 – Installation of vehicle activated sign using 2-way temporary traffic lights in operation Monday to Friday between 9.30am and 3.30pm.
Bridge Schemes
High Street, Marlow – Marlow Bridge : Monday 10th May 2021 to Friday 16th December 2022 – Major bridge refurbishment using a footway closure when appropriate in operation Monday to Friday between 8.00am and 5.00pm.